engineering report · M-8
M-8 - City Engineer Report
Page 3 of 3
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
December 21, 2023
PROJECT UPDATE
Upcoming Infrastructure Description Next Steps/Schedule
Project
The current wastewater treatment facility (WWTF) has a
Final Compliance with NPDES
chloride compliance schedule. There is not any wastewater
Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of
MSA presented its findings on
meeting compliance. The existing treatment facility is at about
Wastewater Treatment Improvements November 1st, 2022. MSA has
50% capacity. However, if the past growth rate continues an
prepared a proposed schedule
expansion will be required in the next 5-7 years.
for wastewater treatment, water
treatment and water supply
From design to construction the process typically takes 3-4
improvement projects.
years.
DOT has requested concurrence from the City on permanent
Deer View Avenue and Tall Grass
improvements to intersection within 5 years of installation of
Avenue & Hwy 6 Intersection TBD
temporary traffic signals in 2020. Scope includes both
Improvements
pedestrian and vehicle accommodations.
Reviewed options for sanitary routing to subdivision and
Hickory Knoll Sanitary Sewer TBD
provided opinions of cost to City for review.
MSA is working on permitting and solicitations for adding an
RRFB flashing pedestrian sign on the eastern leg of the
Pedestrian light (RRFB) on eastern leg
roundabout at Hwy 6 & Park Road. We will be submitting this Spring/Summer 2024
of roundabout at Hwy 6 & Park Road.
over the winter and will seek installation after the trail
improvement project to the soccer fields is complete.
PROJECT UPDATE
Page 3 of 3