contract agreement · K-3
K-3 - Pay Estimate 3 - Boomerang - Potter Creek Interceptor Project
Page 2 of 3
Text read by the vision model; check the PDF for anything that matters.PARTIAL PAYMENT ESTIMATE NUMBER 3
CONTRACTOR: Boomerang Corp.
ADDRESS: 13225 Circle Dr, Suite A, PO Box 227
CITY, STATE, ZIP Anamosa, IA 52205
OWNER: CITY OF TIFFIN
PROJECT: Potter Creek Interceptor Sewer Project
HFC#21218.244
<table>
<tr>
<th>Date of Completion:</th>
<th>Amount of Contract:</th>
<th>Date of Estimate:</th>
</tr>
<tr>
<td>Original: 9/1/2024</td>
<td>Original: $1,067,837.60</td>
<td>From: 17-Dec-23</td>
</tr>
<tr>
<td>Revised:</td>
<td>Revised: $1,073,277.40 (C.O. #1)</td>
<td>To: 27-Feb-24</td>
</tr>
</table>
<table>
<tr>
<th></th>
<th>THIS PERIOD</th>
<th>TOTAL TO DATE</th>
</tr>
<tr>
<td>Amount Earned</td>
<td>$375,848.00</td>
<td>$1,110,539.40</td>
</tr>
<tr>
<td>Add Material Stored On-Site</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>Subtract Materials Installed On-Site</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>Subtotal</td>
<td>$375,848.00</td>
<td>$1,110,539.40</td>
</tr>
<tr>
<td>Retainage (5%)</td>
<td>$18,792.40</td>
<td>$55,526.97</td>
</tr>
<tr>
<td>Previous Payments</td>
<td></td>
<td>$697,956.83</td>
</tr>
<tr>
<td>Amount Due</td>
<td>$357,055.60</td>
<td>$357,055.60</td>
</tr>
</table>
Estimated % of Job Complete Based on Amount Earned/Contract Amount only 104%
This does not constitute work completed to date
Is Contractor's Construction Progress on Schedule? YES X NO N/A
I hereby certify that I have carefully inspected the work and as a result of my inspection and to the best of my knowledge and belief, the quantities shown in this estimate are correct and have not been shown in previous estimates and the work has been performed in accordance with the contract documents.
HART-FREDERICK CONSULTANTS P.C.
By: [signature]
Title: Project Engineer
Date: February 28, 2024
Approved by Owner's Representative:
By: ________________________________
Title: ________________________________
(Additional signatures -- if required)
By: ________________________________
Title: ________________________________