K-3 - Change Order 1 - Rathje Construction - Original Town Phase 3
Page 2 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER REQUEST
DATE: 8/2/2024
CONTRACT # 0
CHANGE ORDER REQUEST NO. 1R
PROJECT: Tiffin Phase 3 Reconstruction Project
CONTRACTOR: Rathje Construction
CONTRACTOR PROJECT MANAGER: Dan Scofield
CITY OF TIFFIN CONSTRUCTION PROJECT MANAGER: Ben Carhoff
DESCRIPTION OF REQUEST:
1. After failing a proof roll at the intersection of Third Street And Summerhayes street, it was requested we submitt a price for Subgrade Stabilization, Polymer Grid and and additional 6" of subgrade rock. The price increase from the 1st Change Order Request is due to the crew needing to spot all utilities while doing the additional core out and rock installation. We will also have to us smaller rubber track skid loader to grade with not to damage the utilities. The job was bid using a dozer and placing the material at a faster rate.
2. Subgrade Stabilization, Polymer Grid is highly recommended to help bridge the soft areas. Manufacturers recommendation is to use 12" of subbase with this product.
3. Utility delays and conflicts are for the time of our crew locating utilities that are in conflict with our proposed Storm Pipe runs. We have to expose the utility conflict, wait for the utility company to schedule their crews to raise or lower the conflict, then move back down to that area to finish our work. This work was done at the Intersection of Brown Street And Third Street, in 2 seperate locations. This will also establish a unit price to use if needed for future conflicts. Time can be agreed upon between Rathje foreman and the inspector.
SUDAS SPECIFICATION SECTION TO SUPPORT REQUEST, DIVISION 1:
JUSTIFICATION FOR THE REQUEST, WORKING DIVISION:
<table>
<tr>
<th>Line No.</th>
<th>Item No.</th>
<th>Item Description</th>
<th>Quantity</th>
<th>Unit</th>
<th>Unit Price</th>
<th>Mark up</th>
<th>Unit Price w/ Markup</th>
<th>Working Days Requested</th>
<th>Proposed Increase (Decrease) in Contract Price</th>
</tr>
<tr>
<td>1</td>
<td></td>
<td>Subgrade Stabilization, 6"</td>
<td>346.00</td>
<td>CY</td>
<td>$75.00</td>
<td>0.00%</td>
<td>$75.00</td>
<td>8</td>
<td>$25,950.00</td>
</tr>
<tr>
<td>2</td>
<td></td>
<td>Subgrade Stabilization, Polymer Grid</td>
<td>2077.11</td>
<td>SY</td>
<td>$3.50</td>
<td>0.00%</td>
<td>$3.50</td>
<td>0</td>
<td>$7,269.89</td>
</tr>
<tr>
<td>3</td>
<td></td>
<td>Utility Delays/conflicts</td>
<td>8.00</td>
<td>HR</td>
<td>$450.00</td>
<td>0.00%</td>
<td>$450.00</td>
<td>0</td>
<td>$3,600.00</td>
</tr>
<tr>
<td colspan="8">Net Increase (Decrease)</td>
<td>8</td>
<td>$36,819.89</td>
</tr>
</table>
SUPPORT DOCUMENTS INCLUDED:
CONTRACT TIME IMPACT: ____________________ (N/A)
REVISED SCHEDULE PROVIDED? YES or NO
STANDARD SUDAS BID ITEMS MUST BE USED IF POSSIBLE, OTHERWISE PROVIDE COST BREAKDOWN:
INVOICES (REQUIRED):
MATERIAL SUBMITTALS (REQUIRED):
ADDITIONAL SUPPORT DOCUMENTS INCLUDED:
This document does not change the Contract Price or Contract Time but is evidence that the parties expect that the subject changes will be incorporated into a subsequent Contract Change Order following negotiation by the parties as to effect, if any, upon Contract Price or Contract Time. Work shall not be deemed acknowledged per Division 1, General Provisions and Covenants until all signatures are received. Payment related to this document will only be made after execution of Contract Change Order through City Council.