Text read by the vision model; check the PDF for anything that matters.CITY OF TIFFIN - COMMUNITY RECREATION CENTER
Construction Manager @ Risk - Evaluation Summary
Release Date: November 15, 2024
Summary:
On Tuesday, November 5th, Statement of Qualifications (SOQ) were received by the city of Tiffin. All 10 firms that submitted statements were deemed qualified and were issued a Request for Proposal (RFP) on Tuesday, November 6th. Eight (8) Proposals were received on Tuesday, November 12th. The SOQ’s and Proposals were reviewed and evaluated by a 5 member committee (2 Council Members, 2 City Staff, Mayor).
SOQ’s were scored on a 100 point scale, and Proposals were scored on a 75 point scale. The committee elected to score SOQ’s with 5 point increments and set the average score for each at half of the total category points. Higher or reduced scores were based on how well the information submitted related to the RFQ sections and other submitting firms. Proposals were scored in 5 point increments based on ranking combined fee total utilizing a $9.5 Million budget. There was a total of 175 points possible and the results are shown below.
<table>
<tr>
<th rowspan="2">Firm</th>
<th colspan="3">Evaluation Summary</th>
</tr>
<tr>
<th>SOQ Score (100 Points)</th>
<th>Proposal Score (75 Points)</th>
<th>Total (175 Points)</th>
</tr>
<tr>
<td>Miron Construction</td>
<td>90</td>
<td>70</td>
<td>160</td>
</tr>
<tr>
<td>Conlon Construction</td>
<td>90</td>
<td>45</td>
<td>135</td>
</tr>
<tr>
<td>Woodruff Construction</td>
<td>70</td>
<td>65</td>
<td>135</td>
</tr>
<tr>
<td>Portzen Construction</td>
<td>30</td>
<td>75</td>
<td>105</td>
</tr>
<tr>
<td>City Construction</td>
<td>45</td>
<td>60</td>
<td>105</td>
</tr>
<tr>
<td>DCI Group</td>
<td>45</td>
<td>50</td>
<td>95</td>
</tr>
<tr>
<td>Opus Group</td>
<td>40</td>
<td>55</td>
<td>95</td>
</tr>
<tr>
<td>Dean Snyder Construction</td>
<td>40</td>
<td>40</td>
<td>80</td>
</tr>
<tr>
<td>McComas-Lacina Construction</td>
<td>65</td>
<td>DNS</td>
<td>65</td>
</tr>
<tr>
<td>Larson Construction</td>
<td>35</td>
<td>DNS</td>
<td>35</td>
</tr>
</table>
As a result of this process, the committee has selected Miron Construction as the Construction Manager at Risk for the city of Tiffin Recreation Center project. A formal recommendation will be made to the City Council at their November 19th Council meeting. Thank you to all of the firms that submitted. The time and effort it took to prepare your submissions is greatly appreciated.