contract agreement · K-5
K-5 - Professional Services Predesign Agreement with DOT - Highway 6 Improvements
Page 1 of 7
Text from the PDF text layer; check the PDF for anything that matters.January 2023
IOWA DEPARTMENT OF TRANSPORTATION
Predesign Agreement
For Primary Road Project
County Johnson
City Tiffin
Project No. STP-006-7(098)--2C-52
PCC Pavement - Grade &
Replace
STPN-006-7(101)--2J-52
PCC Sidewalk/Trail
BRF-006-7(102)--38-52
RCB Culvert Replacement -
Twin Box
Iowa DOT
Agreement No. 2025-P-001
Staff Action No.
This Agreement, is entered into by and between the Iowa Department of Transportation, designated the
"DOT", and the city of Tiffin, Iowa, a Local Public Agency, designated the "LPA" in accordance with Iowa
Code Chapters 28E, 306, 306A and 313.4 as applicable;
The DOT proposes to establish or make improvements to U.S. 6 within Johnson County, Iowa; and
The DOT and the LPA intend to jointly participate in said project, in the manner provided herein and
This Agreement reflects the current concept of this project which is subject to modification by mutual
agreement between the LPA and the DOT; and
Therefore, it is agreed as follows:
1. Project Information
a. The LPA shall design the roadway improvements; and the DOT shall design and acquire the
necessary right of way, obtain the necessary environmental and cultural clearances, let, and inspect
construction of the following described project in accordance with the project plans and DOT
Standard Specifications:
U.S. 6 (Marengo Road) will be reconstructed with Portland cement concrete (PCC) pavement
within the city of Tiffin from Grant Street to Park Road. See Exhibit A for project location.
2. Funding Sources
a. The following funding sources have been identified for the project (see Exhibit B):
Iowa DOT $4,067,348
City of Tiffin $3,954,292
Total Funding $8,021,640
b. The LPA shall be responsible for 33% of the costs for Excavation and Removals and 30% of the cost
for Paving for the following improvements:
(1) Widening of U.S. 6 pavement, and side road reconstruction at the following locations, estimated
cost $986,154
2025-P-001_Tiffin 1
Sources
- sharepoint (K-5 - Professional Services Predesign Agreement with DOT - Highway 6 Improvements.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.