contract agreement · K-7
K-7 - Guaranteed Maximum Price Amendment - Miron
Page 10 of 10
Text from the PDF text layer; check the PDF for anything that matters. Exhibit 3 - Drawings
Drawing No. Drawing Title Date Revision# Set Name
A0.1 Title Sheet 04/04/25 0 BP #1 Drawings - 040425
A1.1 Building Information Plan 04/04/25 0 BP #1 Drawings - 040425
A1.2 Site Plan 04/04/25 0 BP #1 Drawings - 040425
A1.3 Site Plan 04/04/25 0 BP #1 Drawings - 040425
A2.1 Main Level Floor Plan 04/04/25 0 BP #1 Drawings - 040425
A2.2 Second Level Floor Plan And & Assembly Types 04/14/25 1 BP #1- Add #1 - 041525
A2.4 Enlarged Floor Plans 04/14/25 1 BP #1- Add #1-041525
A2.5 Enlarged Floor Plan 04/04/25 0 BP #1 Drawings - 040425
A2.6 Schedules 04/04/25 0 BP #1 Drawings - 040425
A3.1 Exterior Elevations 04/14/25 1 BP #1- Add #1 - 041525
A3.2 Building Sections 04/14/25 1 BP #1- Add #1 - 041525
A3.3 Building Sections 04/14/25 1 BP #1- Add #1- 041525
A3.4 Wall Sections 04/04/25 0 BP #1 Drawings - 040425
A3.5 Wall Sections 04/04/25 0 BP #1 Drawings - 040425
A3.6 Elevator Sections & Details 04/04/25 0 BP #1 Drawings - 040425
A3.7 Stairs Sections 04/04/25 0 BP #1 Drawings - 040425
A4.1 Roof Plan 04/04/25 0 BP #1 Drawings - 040425
A5.1 Interior Elevations 03/28/25 0 BP #1 Drawings - 040425
A5.2 Interior Elevations 03/28/25 0 BP #1 Drawings - 040425
A6.1 Reflected Ceiling Plan 04/04/25 0 BP #1 Drawings - 040425
A6.2 Reflected Ceiling Plan 04/21/25 1 BP #1- Add #1 - 041525
C1 Title Sheet 04/04/25 0 BP #1 Drawings - 040425
C2 Details 04/04/25 0 BP #1 Drawings - 040425
C3 Overall Existing Conditions & Demolition 04/04/25 0 BP #1 Drawings - 040425
C4 Overall Paving & Geometric 04/21/25 1 BP #1- Add #2 - 042225
C5 Building Geometric & Paving 04/21/25 1 BP #1 - Add #2 - 042225
C6 Overall Grading Plan 04/21/25 1 BP #1 - Add #2 - 042225
C7 Building Grading Plan 04/04/25 0 BP #1 Drawings - 040425
C8 Overall Utility Plan 04/21/25 1 BP #1- Add #2 - 042225
C9 Sanitary P&P 04/21/25 1 BP #1- Add #2 - 042225
C10 Stormwater Pollution Prevention 04/04/25 0 BP #1 Drawings - 040425
C11 Erosion Control Details 04/04/25 0 BP #1 Drawings - 040425
c12 Overall Erosion Control 04/21/25 1 BP #1 - Add #2 - 042225
S0.1 General Notes & Schedules 04/21/25 1 BP #1 - Add #2 - 042225
S0.2 Typical Details 04/04/25 0 BP #1 Drawings - 040425
S1 .1 Foundation Plan 04/21/25 1 BP #1- Add #2 - 042225
S2.1 Second Floor Framing Plan 04/04/25 0 BP #1 Drawings - 040425
MOO0 General Notes 04/04/25 0 100 % DD Drawings - 040425
M101 Main Floor Mechanical Plan 04/04/25 0 100 % DD Drawings - 040425
M102 Second Floor Mechanical Plan 04/04/25 0 100 % DD Drawings - 040425
M301 Mechanical Details 04/04/25 0 100 % DD Drawings - 040425
M401 Mechanical Controls 04/04/25 0 100 % DD Drawings - 040425
M402 Mechanical Controls 04/04/25 0 100 % DD Drawings - 040425
M501 Mechanical Schedules 04/04/25 0 100 % DD Drawings - 040425
M502 Mechanical Schedules 04/04/25 0 100 % DD Drawings - 040425
P100 Underground Plumbing Plan 04/04/25 0 100 % DD Drawings - 040425
P110 Main Floor Plumbing Plan 04/04/25 0 100 % DD Drawings - 040425
P111 Second Floor Plumbing Plan 04/04/25 0 100 % DD Drawings - 040425
P301 Plumbing Details 04/04/25 0 100 % DD Drawings - 040425
P501 Plumbing Schedules 04/04/25 0 100 % DD Drawings - 040425
P502 Plumbing Schedules 04/04/25 0 100 % DD Drawings - 040425
F101 Main Floor Fire Protection Plan 04/04/25 0 100 % DD Drawings - 040425
F102 Second Floor Fire Protection Plan 04/04/25 0 100 % DD Drawings - 040425
E000 Electrical General Notes 04/04/25 0 100 % DD Drawings - 040425
E001 Site Plan - Power And Lighting 04/04/25 0 100 % DD Drawings - 040425
E101 Main Level Floor Plan - Power 04/04/25 0 100 % DD Drawings - 040425
E102 Second Level Floor Plan - Power 04/04/25 0 100 % DD Drawings - 040425
E201 Main Level Ceiling Plan - Lighting 04/04/25 0 100 % DD Drawings - 040425
E202 Second Level Ceiling Plan - Lighting 04/04/25 0 100 % DD Drawings - 040425
E401 Electrical Details 04/04/25 0 100 % DD Drawings - 040425
E501 Electrical Schedules 04/04/25 0 100 % DD Drawings - 040425
E502 Electrical Schedules 04/04/25 0 100 % DD Drawings - 040425
TT101 Main Level Floor Plan - Technology 04/04/25 0 100 % DD Drawings - 040425
TT102 Second Level Floor Plan - Technology 04/04/25 0 100 % DD Drawings - 040425
May 6, 2025
Sources
- sharepoint (K-7 - Guaranteed Maximum Price Amendment - Miron.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.