Text from the PDF text layer; check the PDF for anything that matters.MISCELLANEOUS ITEMS TOTALS THIS PERIOD COMPLETED TO DATE
Item # Description Quantity Unit Unit Price Total Quantity Cost Quantity Cost %
1 Traffic Control 1 LS $ 12,000.00 $ 12,000.00 0.00 $ - 0.50 $ 6,000.00 50.00%
2 Rock Check Dam 24 EA $ 750.00 $ 18,000.00 0.00 $ - 6.00 $ 4,500.00 25.00%
3 Class D Rip Rap 52 TON $ 60.00 $ 3,120.00 0.00 $ - 0.00 $ - 0.00%
4 Silt fence 1,475 LF $ 2.00 $ 2,950.00 827.00 $ 1,654.00 1,127.00 $ 2,254.00 76.41%
5 Filter Sock Inlet Protection 7 EA $ 75.00 $ 525.00 0.00 $ - 4.00 $ 300.00 57.14%
6 Seeding Work 4.8 ACRE $ 4,700.00 $ 22,560.00 0.83 $ 3,901.00 0.83 $ 3,901.00 17.29%
7 Finish Grading 1 LS $ 16,000.00 $ 16,000.00 0.00 $ - 0.50 $ 8,000.00 50.00%
8 SWPPP Maintenance 1 LS $ 2,800.00 $ 2,800.00 0.00 $ - 0.00 $ - 0.00%
MISCELLANEOUS TOTAL $ 77,955.00 $ 5,555.00 $ 24,955.00
EXTRA WORK ORDERS TOTALS THIS PERIOD COMPLETED TO DATE
Item # Description Quantity Unit Unit Price Total Quantity Cost Quantity Cost %
1 Pipe Upsize: 8" Truss to 10" Truss Per City 1 LS $ 10,215.20 $ 10,215.20 0.00 $ - 0.00 $ - 0.00%
2 Trench Stabilization 33.33 TON $ 38.00 1,266.54 33.33 $ 1,266.54 33.33 $ 1,266.54 100.00%
3 2" x 4" Oversized Material 56.08 TON $ 42.00 2,355.36 56.08 $ 2,355.36 56.08 $ 2,355.36 100.00%
EXTRA WORK ORDER COST $ 13,837.10 $ 3,621.90 $ 3,621.90
Summary of Request
Total Contract $ 870,652.60 $ 67,330.20 $ 568,253.20
Extra Work Orders $ 13,837.10 $ 3,621.90 $ 3,621.90
Total Contract w/ EWOs $ 884,489.70 $ 70,952.10 $ 571,875.10 % Complete:
64.66%
Less Retainage of Completed Work (0%) $ -
Total Retainage / Dues $ -
Total Earned Less Retainage $ 571,875.10 To finish (w/ret.):
Less Previously Approved Pay Requests $ - $312,614.60
Previously Approved Pay Requests: PAID? DATE
Pay App #1 $ 500,923.00
Total Previously Approved Pay Requests $ 500,923.00 Balance Due This Month $ 70,952.10
Balance Overdue $ -
Total Balance Due $ 70,952.10
Thank you!
1 1/2% (18% per annum) per month late payment charge will be added to accounts 30 days past due.
67.5% per developer's agreement
$47,892.67
Page 2 of 2
Sources
- sharepoint (K-3 - Tiffin Heights West Public Improvements Pay App 2 & Pay App 3.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.