WS - C - Village Drive Extension Cost Estimates
Page 6 of 7
Text read by the vision model; check the PDF for anything that matters.ESTIMATED CONSTRUCTION COSTS
PROJECT: VILLAGE DRIVE EXTENSION - ADJACENT TO BURD PROPERTY
LOCATION: Tiffin, Iowa
DATE: February 7, 2024
TOTAL COST ADJACENT TO BURD PROPERTY
<table>
<tr>
<th>ITEM NO.</th>
<th>ITEM CODE</th>
<th>DESCRIPTION</th>
<th>UNIT</th>
<th>EST Quant.</th>
<th>UNIT PRICE</th>
<th>TOTAL PRICE</th>
</tr>
<tr>
<th colspan="7">TOTAL QUANTITIES</th>
</tr>
<tr>
<td>1</td>
<td>2010-D</td>
<td>Strip, Stockpile, and Repspread Topsoil (6")</td>
<td>CY</td>
<td>580</td>
<td>$8.60</td>
<td>$4,988.00</td>
</tr>
<tr>
<td>2</td>
<td>2010-E</td>
<td>Excavation, Class 10</td>
<td>CY</td>
<td>1,300</td>
<td>$3.40</td>
<td>$4,420.00</td>
</tr>
<tr>
<td>3</td>
<td>2010-G</td>
<td>Subgrade Prep, Roadway</td>
<td>SY</td>
<td>1,052</td>
<td>$1.95</td>
<td>$2,051.40</td>
</tr>
<tr>
<td>4</td>
<td>2010-I</td>
<td>Subbase, Modified, 6-inch Thick (Street)</td>
<td>SY</td>
<td>1,052</td>
<td>$7.40</td>
<td>$7,784.80</td>
</tr>
<tr>
<td>5</td>
<td>4040-A</td>
<td>Subdrain Tile, HDPE With Porous Backfill, 6" Dia.</td>
<td>LF</td>
<td>480</td>
<td>$16.30</td>
<td>$7,824.00</td>
</tr>
<tr>
<td>6</td>
<td>5010-A</td>
<td>Water Main With Fittings, Trenched, 8" Dia. PVC</td>
<td>LF</td>
<td>206</td>
<td>$50.10</td>
<td>$10,320.60</td>
</tr>
<tr>
<td>7</td>
<td>5020-C</td>
<td>Fire Hydrant Assembly</td>
<td>EA</td>
<td>1</td>
<td>$7,200.00</td>
<td>$7,200.00</td>
</tr>
<tr>
<td>8</td>
<td>7010-A</td>
<td>Pavement, Mainline PCC, 8" Thick (31' assumed)</td>
<td>SY</td>
<td>891.0</td>
<td>$55.30</td>
<td>$49,272.30</td>
</tr>
<tr>
<td>9</td>
<td>9010-B</td>
<td>Hydraulic Seeding, Fertilizing, and Mulching</td>
<td>Ac</td>
<td>0.50</td>
<td>$3,250.00</td>
<td>$1,625.00</td>
</tr>
<tr>
<th colspan="6">TOTAL COST ADJACENT TO PURD PROPERTY (less sidewalk) =</th>
<th>$95,486.10</th>
</tr>
<tr>
<td></td>
<td>7030-E</td>
<td>Sidewalk, PCC, 4" - 6' Wide (South Side Only)</td>
<td>SY</td>
<td>160.0</td>
<td>$30.00</td>
<td>$4,800.00</td>
</tr>
<tr>
<th colspan="6">BURD PORTION =</th>
<th>$52,543.05</th>
</tr>
<tr>
<th colspan="6">THE VILLAGES PORTION =</th>
<th>$47,743.05</th>
</tr>
</table>
Sources
- sharepoint (WS - C - Village Drive Extension Cost Estimates.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (WS - C - Village Drive Extension Cost Estimates.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.