WS - C - Village Drive Extension Cost Estimates
Page 4 of 7
Text read by the vision model; check the PDF for anything that matters.ESTIMATED CONSTRUCTION COSTS
PROJECT: VILLAGE DRIVE EXTENSION - CITY OF TIFFIN PORTION (OVERWIDTH AND OVERSIZE)
LOCATION: Tiffin, Iowa
DATE: February 7, 2024
<table>
<tr>
<th>ITEM NO.</th>
<th>DESCRIPTION</th>
<th>UNIT</th>
<th>EST Quant.</th>
<th>UNIT PRICE</th>
<th>TOTAL PRICE</th>
</tr>
<tr>
<td colspan="6">** WATER MAIN CALCULATIONS **</td>
</tr>
<tr>
<td colspan="6">OVERSIZE CALCULATIONS</td>
</tr>
<tr>
<td>1</td>
<td>Water Main With Fittings, Trenched, 16" Dia. PVC</td>
<td>LF</td>
<td>2,349</td>
<td>$134.50</td>
<td>$315,940.50</td>
</tr>
<tr>
<td>2</td>
<td>Water Main With Fittings, Trenched, 12" Dia. PVC</td>
<td>LF</td>
<td>195</td>
<td>$85.00</td>
<td>$16,575.00</td>
</tr>
<tr>
<td>3</td>
<td>MJ Butterfly Valve, 16" Dia. complete with Valve Box</td>
<td>EA</td>
<td>7</td>
<td>$4,925.00</td>
<td>$34,475.00</td>
</tr>
<tr>
<td>4</td>
<td>MJ Gate Valve, 12" Dia. complete with Valve Box</td>
<td>EA</td>
<td>1</td>
<td>$3,200.00</td>
<td>$3,200.00</td>
</tr>
<tr>
<td colspan="5">Oversized Water Main and Valve Total =</td>
<td>$370,190.50</td>
</tr>
<tr>
<td colspan="6">STANDARD SIZE CALCULATIONS</td>
</tr>
<tr>
<td>5</td>
<td>Water Main With Fittings, Trenched, 8" Dia. PVC</td>
<td>LF</td>
<td>2,544</td>
<td>$50.10</td>
<td>$127,454.40</td>
</tr>
<tr>
<td>6</td>
<td>MJ Gate Valve, 8" Dia. complete with Valve Box</td>
<td>EA</td>
<td>8</td>
<td>$2,400.00</td>
<td>$19,200.00</td>
</tr>
<tr>
<td colspan="5">Standard Water Main and Valve Total =</td>
<td>$146,654.40</td>
</tr>
<tr>
<td colspan="6">CITY'S WATER MAIN OVERWIDTH PORTION = $223,536.10</td>
</tr>
<tr>
<td colspan="6">** PAVING CALCULATIONS **</td>
</tr>
<tr>
<td colspan="6">OVERWIDTH CALCULATIONS (40')</td>
</tr>
<tr>
<td>7</td>
<td>Pavement, Mainline PCC, 8" Thick (40' assumed)</td>
<td>SY</td>
<td>11,307</td>
<td>$55.30</td>
<td>$625,277.10</td>
</tr>
<tr>
<td>8</td>
<td>Subbase, Modified, 6-inch Thick</td>
<td>SY</td>
<td>12,733</td>
<td>$7.40</td>
<td>$94,224.20</td>
</tr>
<tr>
<td>9</td>
<td>Subgrade Prep, Roadway</td>
<td>SY</td>
<td>12,733</td>
<td>$1.95</td>
<td>$24,829.35</td>
</tr>
<tr>
<td colspan="5">40' Street Total =</td>
<td>$744,330.65</td>
</tr>
<tr>
<td colspan="6">STANDARD WIDTH CALCUALTIONS (31')</td>
</tr>
<tr>
<td>10</td>
<td>Pavement, Mainline PCC, 8" Thick (31' assumed)</td>
<td>SY</td>
<td>8,773</td>
<td>$55.30</td>
<td>$485,146.90</td>
</tr>
<tr>
<td>11</td>
<td>Subbase, Modified, 6-inch Thick</td>
<td>SY</td>
<td>10,205</td>
<td>$7.40</td>
<td>$75,517.00</td>
</tr>
<tr>
<td>12</td>
<td>Subgrade Prep, Roadway</td>
<td>SY</td>
<td>10,205</td>
<td>$1.95</td>
<td>$19,899.75</td>
</tr>
<tr>
<td colspan="5">31' Street Total =</td>
<td>$580,563.65</td>
</tr>
<tr>
<td colspan="6">CITY'S STREET PAVING OVERWIDTH PORTION = $163,767.00</td>
</tr>
<tr>
<td colspan="6">** SIDEWALK CALCULATIONS **</td>
</tr>
<tr>
<td colspan="6">OVERWIDTH CALCULATIONS</td>
</tr>
<tr>
<td>13</td>
<td>Sidewalk, PCC, 6" (10' Wide, North Side Only)</td>
<td>SY</td>
<td>2,797</td>
<td>$41.50</td>
<td>$116,075.50</td>
</tr>
<tr>
<td>14</td>
<td>Subbase, Modified, 6-inch Thick</td>
<td>SY</td>
<td>2,797</td>
<td>$7.40</td>
<td>$20,697.80</td>
</tr>
<tr>
<td>15</td>
<td>Subgrade Prep - North Sidewalk</td>
<td>SY</td>
<td>2,797</td>
<td>$1.95</td>
<td>$5,454.15</td>
</tr>
<tr>
<td colspan="5">10' Sidewalk/Trail Total =</td>
<td>$142,227.45</td>
</tr>
<tr>
<td colspan="6">STANDARD CALCULATIONS</td>
</tr>
<tr>
<td>16</td>
<td>Sidewalk, PCC, 4" (6' Wide, North Side Only)</td>
<td>SY</td>
<td>1,679</td>
<td>$30.00</td>
<td>$50,370.00</td>
</tr>
<tr>
<td>17</td>
<td>Subgrade Prep - North Sidewalk</td>
<td>SY</td>
<td>1,679</td>
<td>$1.95</td>
<td>$3,274.05</td>
</tr>
<tr>
<td colspan="5">6' Sidewalk Total =</td>
<td>$53,644.05</td>
</tr>
<tr>
<td colspan="6">CITY'S TRAIL OVERWIDTH PORTION = $88,583.40</td>
</tr>
<tr>
<td colspan="5">TOTAL CITY PORTION =</td>
<td>$475,886.50</td>
</tr>
</table>
Sources
- sharepoint (WS - C - Village Drive Extension Cost Estimates.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (WS - C - Village Drive Extension Cost Estimates.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.