I-5 - Resolution 2025-068 - Approving Partial Release of Escrow for Tiffin West
Page 5 of 5
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th rowspan="2">ITEM NO.</th>
<th rowspan="2">DESCRIPTION OF WORK</th>
<th colspan="3">WORK COMPLETED</th>
<th rowspan="2">MATERIALS PRESENTLY STORED (NOT IN D OR E)</th>
<th rowspan="2">TOTAL COMPLETED AND STORED TO DATE (D+E+F)</th>
<th rowspan="2">% (G ÷ C)</th>
<th rowspan="2">BALANCE TO FINISH (C - G)</th>
<th rowspan="2">RETAINAGE (IF VARIABLE RATE)</th>
</tr>
<tr>
<th>SCHEDULED VALUE</th>
<th>FROM PREVIOUS APPLICATION (D + E)</th>
<th>THIS PERIOD</th>
</tr>
<tr>
<td>1</td>
<td>Mass Grading</td>
<td>441,665.00</td>
<td>441,665.00</td>
<td>0.00</td>
<td>0.00</td>
<td>441,665.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>2</td>
<td>Structure Demolition & Site Clearing</td>
<td>99,145.00</td>
<td>99,145.00</td>
<td>0.00</td>
<td>0.00</td>
<td>99,145.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>3</td>
<td>Underground Utilities</td>
<td>145,055.00</td>
<td>145,055.00</td>
<td>0.00</td>
<td>0.00</td>
<td>145,055.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>4</td>
<td>Onsite Paving</td>
<td>142,595.00</td>
<td>142,595.00</td>
<td>0.00</td>
<td>0.00</td>
<td>142,595.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>5</td>
<td>Offsite Improvements</td>
<td>260,058.99</td>
<td>260,058.99</td>
<td>0.00</td>
<td>0.00</td>
<td>260,058.99</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>5A</td>
<td>Credit OG Offsite Package</td>
<td>(260,058.99)</td>
<td>(260,058.99)</td>
<td>0.00</td>
<td>0.00</td>
<td>(260,058.99)</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>5B</td>
<td>Updated Offsite Package</td>
<td>410,309.75</td>
<td>410,309.75</td>
<td>0.00</td>
<td>0.00</td>
<td>410,309.75</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>5C</td>
<td>Additional Offsite Package</td>
<td>68,110.50</td>
<td>68,110.50</td>
<td>0.00</td>
<td>0.00</td>
<td>68,110.50</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>6</td>
<td>4" of Topsoil & Install Silt Fence on Slope</td>
<td>9,746.25</td>
<td>9,746.25</td>
<td>0.00</td>
<td>0.00</td>
<td>9,746.25</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>7</td>
<td>Tiffin West Revised Plans</td>
<td>172,872.00</td>
<td>172,872.00</td>
<td>0.00</td>
<td>0.00</td>
<td>172,872.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>8</td>
<td>R-1 Water Adjustments</td>
<td>(68,764.00)</td>
<td>(68,764.00)</td>
<td>0.00</td>
<td>0.00</td>
<td>(68,764.00)</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>9</td>
<td>Utility & Grading Adjustments</td>
<td>292,226.30</td>
<td>292,226.30</td>
<td>0.00</td>
<td>0.00</td>
<td>292,226.30</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>10</td>
<td>Erosion Control BP #1</td>
<td>63,713.90</td>
<td>63,713.90</td>
<td>0.00</td>
<td>0.00</td>
<td>63,713.90</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>11</td>
<td>Add Erosion Measures & Class E Rip Rap</td>
<td>10,268.00</td>
<td>10,268.00</td>
<td>0.00</td>
<td>0.00</td>
<td>10,268.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>12</td>
<td>Soil Erosion Control</td>
<td>37,675.00</td>
<td>37,675.00</td>
<td>0.00</td>
<td>0.00</td>
<td>37,675.00</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>12A</td>
<td>Soil Erosion Control Deduct</td>
<td>(7,535.00)</td>
<td>(7,535.00)</td>
<td>0.00</td>
<td>0.00</td>
<td>(7,535.00)</td>
<td>100.00%</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<th colspan="3">TOTAL</th>
<th>1,817,082.70</th>
<th>1,817,082.70</th>
<th>0.00</th>
<th>0.00</th>
<th>1,817,082.70</th>
<th>100.00%</th>
<th>0.00</th>
<th>0.00</th>
</tr>
</table>