I-5 - Resolution 2025-068 - Approving Partial Release of Escrow for Tiffin West
Page 3 of 5
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>ITEM</th>
<th>DESCRIPTION</th>
<th>SCHEDULE VALUE</th>
<th>PREVIOUS APPLICATIONS</th>
<th>COMPLETED THIS PERIOD</th>
<th>STORED MATERIAL</th>
<th>COMPLETED STORED</th>
<th>%</th>
<th>BALANCE</th>
<th>RETAINAGE</th>
</tr>
<tr>
<td>1</td>
<td>Mass Grading</td>
<td>441,665.00</td>
<td>441,665.00</td>
<td>0.00</td>
<td>0.00</td>
<td>441,665.00</td>
<td>100.00</td>
<td>0.00</td>
<td>22,083.25</td>
</tr>
<tr>
<td>2</td>
<td>Structure Demolition & Site Clearing</td>
<td>99,145.00</td>
<td>99,145.00</td>
<td>0.00</td>
<td>0.00</td>
<td>99,145.00</td>
<td>100.00</td>
<td>0.00</td>
<td>4,957.25</td>
</tr>
<tr>
<td>3</td>
<td>Underground Utilities</td>
<td>145,055.00</td>
<td>145,055.00</td>
<td>0.00</td>
<td>0.00</td>
<td>145,055.00</td>
<td>100.00</td>
<td>0.00</td>
<td>7,252.75</td>
</tr>
<tr>
<td>4</td>
<td>Onsite Paving</td>
<td>142,595.00</td>
<td>135,975.00</td>
<td>6,620.00</td>
<td>0.00</td>
<td>142,595.00</td>
<td>100.00</td>
<td>0.00</td>
<td>7,129.75</td>
</tr>
<tr>
<td>5</td>
<td>Offsite Improvements</td>
<td>260,058.99</td>
<td>260,058.99</td>
<td>0.00</td>
<td>0.00</td>
<td>260,058.99</td>
<td>100.00</td>
<td>0.00</td>
<td>13,002.95</td>
</tr>
<tr>
<td>5A</td>
<td>Credit OG Offsite Package</td>
<td>-260,058.99</td>
<td>-260,058.99</td>
<td>0.00</td>
<td>0.00</td>
<td>-260,058.99</td>
<td>100.00</td>
<td>0.00</td>
<td>-13,002.95</td>
</tr>
<tr>
<td>5B</td>
<td>Updated Offsite Package</td>
<td>410,309.75</td>
<td>16,412.39</td>
<td>393,897.36</td>
<td>0.00</td>
<td>410,309.75</td>
<td>100.00</td>
<td>0.00</td>
<td>20,515.49</td>
</tr>
<tr>
<td>5C</td>
<td>Additional Offsite Package</td>
<td>68,110.50</td>
<td>0.00</td>
<td>68,110.50</td>
<td>0.00</td>
<td>68,110.50</td>
<td>100.00</td>
<td>0.00</td>
<td>3,405.53</td>
</tr>
<tr>
<td>6</td>
<td>4" of Topsoil & Install Silt Fence on Slope</td>
<td>9,746.25</td>
<td>9,746.25</td>
<td>0.00</td>
<td>0.00</td>
<td>9,746.25</td>
<td>100.00</td>
<td>0.00</td>
<td>487.31</td>
</tr>
<tr>
<td>7</td>
<td>Tiffin West Revised Plans</td>
<td>172,872.00</td>
<td>172,872.00</td>
<td>0.00</td>
<td>0.00</td>
<td>172,872.00</td>
<td>100.00</td>
<td>0.00</td>
<td>8,643.60</td>
</tr>
<tr>
<td>8</td>
<td>R-1 Water Adjustments</td>
<td>-68,764.00</td>
<td>-68,764.00</td>
<td>0.00</td>
<td>0.00</td>
<td>-68,764.00</td>
<td>100.00</td>
<td>0.00</td>
<td>-3,438.20</td>
</tr>
<tr>
<td>9</td>
<td>Utility & Grading Adjustmnts</td>
<td>292,226.30</td>
<td>274,692.72</td>
<td>17,533.58</td>
<td>0.00</td>
<td>292,226.30</td>
<td>100.00</td>
<td>0.00</td>
<td>14,611.32</td>
</tr>
<tr>
<td>10</td>
<td>Erosion Control BP#1</td>
<td>63,713.90</td>
<td>63,713.90</td>
<td>0.00</td>
<td>0.00</td>
<td>63,713.90</td>
<td>100.00</td>
<td>0.00</td>
<td>3,185.70</td>
</tr>
<tr>
<td>11</td>
<td>Add Frosion Measures & Class E Rip Rap</td>
<td>10,268.00</td>
<td>10,268.00</td>
<td>0.00</td>
<td>0.00</td>
<td>10,268.00</td>
<td>100.00</td>
<td>0.00</td>
<td>513.40</td>
</tr>
<tr>
<td>12</td>
<td>Soil Erosion Control</td>
<td>37,675.00</td>
<td>30,140.00</td>
<td>7,535.00</td>
<td>0.00</td>
<td>37,675.00</td>
<td>100.00</td>
<td>0.00</td>
<td>1,883.75</td>
</tr>
<tr>
<td>12A</td>
<td>Soil Erosion Control Deduct</td>
<td>-7,535.00</td>
<td>0.00</td>
<td>-7,535.00</td>
<td>0.00</td>
<td>-7,535.00</td>
<td>100.00</td>
<td>0.00</td>
<td>-376.75</td>
</tr>
<tr>
<th colspan="3">REPORT TOTALS</th>
<th>$1,817,082.70</th>
<th>$1,330,921.26</th>
<th>$486,161.44</th>
<th>$0.00</th>
<th>$1,817,082.70</th>
<th>100.00</th>
<th>$0.00</th>
<th>$90,854.15</th>
</tr>
</table>