contract agreement · K-3
K-3 - Pay Estimate 4 - Final - Well 5 Improvements
Page 3 of 3
Text read by the vision model; check the PDF for anything that matters.SUMMARY
<table>
<tr>
<th></th>
<th>Total Approved</th>
<th>Total Completed</th>
</tr>
<tr>
<td>Contract Price</td>
<td>$296,015.00</td>
<td>$290,407.00</td>
</tr>
<tr>
<td rowspan="2">Approved Change Order (list each)</td>
<td>Change Order No. 1</td>
<td>$2,720.00</td>
<td>$1,292.00</td>
</tr>
<tr>
<td>Change Order No. 2</td>
<td>$37,000.00</td>
<td>$37,000.00</td>
</tr>
<tr>
<td colspan="2">Revised Contract Price</td>
<td>$335,735.00</td>
<td>$328,699.00</td>
</tr>
<tr>
<td colspan="2">Stored</td>
<td>Total Earned $328,699.00</td>
<td></td>
</tr>
<tr>
<td colspan="2">Retainage (0%)</td>
<td>$-</td>
<td></td>
</tr>
<tr>
<td colspan="2">Total Earned Less Retainage</td>
<td>$328,699.00</td>
<td></td>
</tr>
</table>
<table>
<tr>
<th>Total Previously Approved (list each)</th>
<th>Pay Estimate No. 1</th>
<th>$131,062.95</th>
</tr>
<tr>
<td></td>
<td>Pay Estimate No. 2</td>
<td>$178,683.60</td>
</tr>
<tr>
<td></td>
<td>Pay Estimate No. 3</td>
<td>$2,517.50</td>
</tr>
<tr>
<td colspan="2">Total Previously Approved</td>
<td>$312,264.05</td>
</tr>
<tr>
<td colspan="2">Amount Due This Request</td>
<td>$16,434.95</td>
</tr>
</table>
Percent Complete 100%
The amount $16,434.95 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By:
Shawver Well Company, Inc.
Recommended By:
Veenstra & Kimm, Inc.
Approved By:
Tiffin, Iowa
Signature: [signature]
Name: Dana V Lentz
Title: Treasurer
Date: 8/18/24
Signature: [signature]
Name: Dave Schechinger
Title: Engineer
Date: August 7, 2024
Signature: [signature]
Name: [name]
Title: [title]
Date: [date]
Sources
- sharepoint (K-3 - Pay Estimate 4 - Final - Well 5 Improvements.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.