Reports from City Personnel — M.9 - Engineer's Report
Page 2 of 3
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
May 29, 2025
PROJECT UPDATE
DEVELOPMENT ASSISTANCE – ANDREW INHELDER
NO FURTHER COMMENTS
Development Name Description
Park Place City Center, Lot 8 No further comments sent on 5/15/24.
Tiffin Heights West On & Off-Site No further comments sent on 10/16/24.
Improvements
Shamrock Center Lot 9 No further comments sent on 12/16/24.
Park Place City Center, Part 1, Lot 3 No further comments sent on 1/29/25.
Tiffin West – Kwik Star No further comments sent on 4/16/25.
Veritas Church Expansion – Phase 2 No further comments sent on 5/15/25
UNDER CONSTRUCTION
Development Name Description
Tiffin Heights West OFF Site All water main along Hwy 6 has passed testing. Sanitary sewer
is complete and is being tested.
Tiffin Heights West ON Site Sanitary sewer is complete and is being tested. Currently
working on water main and storm sewer.
Tiffin West ON & OFF Site Walkthrough performed on 5/28/25. Punch list provided to
developer to be completed in Spring of 2025.
Village Drive Extension (By water tower) Sanitary sewer and roadway grading is under construction.
Construction began 5/22/25.
The States – Anderson Addition OPD Sanitary sewer is currently under construction. Construction
began 5/29/25.
AWAITING RESUBMISSION
Development Name Description
Prairie Village Commercial Part 1, Lot 2 Review comments sent 7/25/23. Awaiting resubmission.
Kimberlite North of Hwy 6 Connection City, Developer, MSA, and DOT met on 8/22/24 to discuss
steps moving forward. Developer to submit proposed
improvements for review.
Prairie West Review comments sent 11/13/24. Awaiting resubmission.
Park Place City Center, Part 3, Lot 1, EMA Review comments sent 2/24/25. Awaiting resubmission.
Storage Building
Hunt Club Phase 4 Review comments sent 3/25/25. Awaiting resubmission.
Village Drive Extension (By water tower) Review comments sent 5/15/25. Awaiting resubmission.
Park Place City Center, Part 4, Phase 4, Lot 22 Review comments sent 5/19/25. Awaiting resubmission.
Bailey Way Extension Review comments sent 5/20/25. Awaiting resubmission.
IN REVIEW
Development Name Description
301 Main Street Site Plan Resubmitted on 5/28/25. In review currently.
PROJECT UPDATE
Page 2 of 3
Sources
- revize: M.9 - Engineer's Report (Y0Lsd0zwKxhM99clyiaOOkThZL2iNp.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (M-9 - City Engineer Report - MSA.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: M Reports from City Personnel
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.