Resolution

Resolution 2024-018

Waiving the City of Tiffin’s 2-Mile Extra-Territorial Review of the Proposed Linn County Rural Electric Cooperative Proposed Substation

adopted · Mar 19, 2024

Timeline

DateStepRecorded inMotion and votes
Mar 19, 2024adopted minutes
meeting 2024-03-19
document
Motion to approve Resolution No. 2024-018 – A Resolution Waiving the City of Tiffin’s 2-Mile Extra- Territorial Review of the Proposed Linn County Rural Electric Cooperative Proposed Substation by Orris
moved Orris, seconded Olney: carried 5 ayes

Documents

Signed copy

Drafts and packet copies

Agendas and minutes citing it

This resolution as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.