contract agreement · K-5
Consideration of Pay Application #2 – Miron Construction, Recreation Center Project – Motion to Approve
Page 3 of 4
Text from the PDF text layer; check the PDF for anything that matters. Miron Construction Co., Inc.
CONTINUATION SHEET AIA DOCUMENT G703
Page: 3
AIA DOCUMENT G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing
Contractor's signed Certification is attached. APPLICATION NUMBER: 2
In tabulation below, amounts are stated to the nearest cent. APPLICATION DATE: 06/23/2025 INVOICE NO.:
Use Column I on Contracts where variable retainage for line items may apply. PERIOD TO: 06/30/2025 250120-0002
PROJECT NO: 250120
A B C D E F G H I
SCHEDULED VALUE WORK COMPLETED (D+E)
TOTAL
MATERIAL
ITEM NO. DESCRIPTION OF WORK FROM COMPLETED PER- BALANCE
CHANGE PRESENTLY RETAINAGE
ORIGINAL CURRENT PREVIOUS THIS PERIOD AND STORED %(GIC) TO FINISH
ORDERS STORED
APPLICATION TO DATE
115 Elevators 122,000.00 0.00 122,000.00 0.00 0.00 0.00 0.00 0 122,000.0( 0.00
120 Fire Suppression 204,120.00 0.00 204,120.00 0.00 0.00 0.00 0.00 0 204,120.0 0.00
125 Plumbing 383,200.00 0.00 383,200.00 0.00 0.00 0.00 0.00 0 383,200.0( 0.00
130 HVAC 935,847.00 0.00 935,847.00 0.00 0.00 0.00 0.00 0 935,847.0( 0.00
135 Electrical 823,355.00 0.00 823,355.00 0.00 0.00 0.00 0.00 0 823,355.0 0.00
140 Earthwork 315,386.00 0.00 315,386.00 0.00 124,613.51 0.00 124,613.51 40 190,772.4 6,230.68
145 Aggregate Piers 135,379.00 0.00 135,379.00 0.00 0.00 0.00 0.00 0 135,379.0( 0.00
150 Asphalt Paving 169,606.00 0.00 169,606.00 0.00 0.00 0.00 0.00 0 169,606.0( 0.00
155 Concrete Site Work 82,800.00 0.00 82,800.00 0.00 0.00 0.00 0.00 0 82,800.0C 0.00
160 Athletic Turf Surfacing 45,000.00 0.00 45,000.00 0.00 0.00 0.00 0.00 0 45,000.0( 0.00
165 Site Utilities 64,708.00 0.00 64,708.00 0.00 18,692.50 0.00 18,692.50 29 46,015.5( 934.63
170 Testing & Inspections Allowance 40,000.00 0.00 40,000.00 0.00 0.00 0.00 0.00 0 40,000.0( 0.00
175 New Utility Services Allowance 40,000.00 0.00 40,000.00 0.00 0.00 0.00 0.00 0 40,000.0( 0.00
180 Mill & Overlay N Parking Lot Allowance 101,000.00 0.00 101,000.00 0.00 0.00 0.00 0.00 0 101,000.0( 0.00
185 Flood Insurance Deductible Allowance 25,000.00 0.00 25,000.00 0.00 0.00 0.00 0.00 0 25,000.0( 0.00
190 CMU Enhancements Allowance 35,000.00 0.00 35,000.00 0.00 0.00 0.00 0.00 0 35,000.0( 0.00
195 Lobby Alternate Ceiling Allowance 45,000.00 0.00 45,000.00 0.00 0.00 0.00 0.00 0 45,000.0( 0.00
200 Data Cabling & Backbone Allowance 250,000.00 0.00 250,000.00 0.00 0.00 0.00 0.00 0 250,000.0( 0.00
205 Access Control Allowance 34,000.00 0.00 34,000.00 0.00 0.00 0.00 0.00 0 34,000.0( 0.00
210 CCTV Allowance 45,000.00 0.00 45,000.00 0.00 0.00 0.00 0.00 0 45,000.0( 0.00
215 Landscaping Allowance 75,000.00 0.00 75,000.00 0.00 0.00 0.00 0.00 0 75,000.0( 0.00
220 Unreleased Add #3 Allowance 10,000.00 0.00 10,000.00 0.00 0.00 0.00 0.00 0 10,000.0( 0.00
Sources
- revize: Attachment (usYiefj1kOSiQeeID3PqZsSZu7EWvo.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-5 - Pay Application 2 - Miron Construction - Recreation Center.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-5 Consideration of Pay Application #2 – Miron Construction, Recreation Center Project –...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.