Text from the PDF text layer; check the PDF for anything that matters. Amount of this Scope: $32,307.00
DESCRIPTION: PCC Upsize (36' - 40')
Phase 1 Paving - Upsize
Item Unit Quantity Unit Price Rate Total
$0.00
8" PCC SY 164 $67.00 164 $10,988.00
$0.00
Subbase Ton 52 $21.00 52 $1,092.00
$0.00
$0.00
$0.00
$0.00
Cost: $12,080.00
Phase 2 Paving - Upsize
Item Unit Quantity Unit Price Rate Total
$0.00
8" PCC SY 262 $67.00 262 $17,554.00
$0.00
Subbase Ton 83 $21.00 83 $1,743.00
$0.00
$0.00
$0.00
$0.00
Cost: $19,297.00
Item/Name Total
PCC Upsize $31,377.00
Bond Increase $930.00
$0.00
$0.00
Total Cost: $32,307.00
Sources
- revize: Item Packet (QrwhVRB8bXdVnyFxxgKTFOz8159L7N.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-3 - Staff Report - Infrastructure Upsizing Reimbursement for Tiffin West – Honey Lane Development.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Consideration of Infrastructure Upsizing Reimbursement for Tiffin West – Honey Lane...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.