contract agreement · K-4
Discussion and Consideration of Pay Application #4 – Miron Construction, Tiffin Recreation Center – Motion to Approve
Page 4 of 5
Text from the PDF text layer; check the PDF for anything that matters. Miron Construction Co., Inc.
CONTINUATION SHEET AIA DOCUMENT G703
Page: 3
AIA DOCUMENT G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing
Contractor's signed Certification is attached. APPLICATION NUMBER: 4
In tabulation below, amounts are stated to the nearest cent. APPLICATION DATE: 08/26/2025 INVOICE NO.:
Use Column I on Contracts where variable retainage for line items may apply. PERIOD TO: 08/31/2025 250120-0004
PROJECT NO: 250120
A B C D E F G H I
SCHEDULED VALUE WORK COMPLETED (D+E)
TOTAL
MATERIAL
FROM COMPLETED PER- BALANCE
ITEM NO. DESCRIPTION OF WORK CHANGE PRESENTLY RETAINAGE
ORIGINAL CURRENT PREVIOUS THIS PERIOD AND STORED %(G/c TO FINISH
ORDERS STORED
APPLICATION TO DATE
115 Elevators 122,000.00 0.00 122,000.00 0.00 0.00 0.00 0.00 0 122,000.0C 0.00
120 Fire Suppression 204,120.00 -75,443.00 128,677.00 0.00 0.00 0.00 0.00 0 128,677.0C 0.00
125 Plumbing 383,200.00 -63,900.00 319,300.00 0.00 0.00 0.00 0.00 0 319,300.0C 0.00
130 HVAC 935,847.00 -215,897.00 719,950.00 0.00 0.00 0.00 0.00 0 719,950.0C 0.00
135 Electrical 823,355.00 -145,415.00 677,940.00 0.00 0.00 0.00 0.00 0 677,940.0C 0.00
140 Earthwork 315,386.00 0.00 315,386.00 173,521.18 0.00 0.00 173,521.18 55 141,864.8 8,676.06
145 Aggregate Piers 135,379.00 0.00 135,379.00 0.00 0.00 0.00 0.00 0 135,379.00 0.00
150 Asphalt Paving 169,606.00 0.00 169,606.00 0.00 0.00 0.00 0.00 0 169,606.00 0.00
155 Concrete Site Work 82,800.00 0.00 82,800.00 0.00 0.00 0.00 0.00 0 82,800.00 0.00
160 Athletic Turf Surfacing 45,000.00 -5,500.00 39,500.00 0.00 0.00 0.00 0.00 0 39,500.00 0.00
165 Site Utilities 64,708.00 7,300.12 72,008.12 31,692.50 0.00 0.00 31,692.50 44 40,315.62 1,584.63
166 Landscaping 0.00 96,515.00 96,515.00 0.00 0.00 0.00 0.00 0 96,515.00 0.00
170 Testing & Inspections Allowance 40,000.00 0.00 40,000.00 3,470.25 0.00 0.00 3,470.25 9 36,529.75 173.51
175 New Utility Services Allowance 40,000.00 0.00 40,000.00 0.00 0.00 0.00 0.00 0 40,000.00 0.00
180 Mill & Overlay N Parking Lot Allowance 101,000.00 0.00 101,000.00 0.00 0.00 0.00 0.00 0 101,000.00 0.00
185 Flood Insurance Deductible Allowance 25,000.00 0.00 25,000.00 0.00 0.00 0.00 0.00 0 25,000.00 0.00
190 CMU Enhancements Allowance 35,000.00 -35,000.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00
195 Lobby Alternate Ceiling Allowance 45,000.00 -45,000.00 0.00 0.00 0.00 0.00 0.00 0 0.0( 0.00
200 Data Cabling & Backbone Allowance 250,000.00 -250,000.00 0.00 0.00 0.00 0.00 0.00 0 0.0( 0.00
205 Access Control Allowance 34,000.00 0.00 34,000.00 0.00 0.00 0.00 0.00 0 34,000.0C 0.00
210 CCTV Allowance 45,000.00 0.00 45,000.00 0.00 0.00 0.00 0.00 0 45,000.0( 0.00
215 Landscaping Allowance 75,000.00 -75,000.00 0.00 0.00 0.00 0.00 0.00 0 O.OC 0.00
Sources
- revize: Attachment (puHyqU2VMW3heCeYZYM6Zz1aM35LRF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Pay App 4 - Miron - Tiffin Recreation Center .pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #4 – Miron Construction, Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.