Discussion and Consideration of Pay Application #4 – Miron Construction, Tiffin Recreation Center – Motion to Approve
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-4
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: August 28, 2025
AGENDA ITEM: Discussion and Consideration of Pay Application #4 – Miron Construction,
Tiffin Recreation Center
ACTION: Motion
Approval
Background
Miron Construction is under contract with the City of Tiffin for the construction of the new
Community Recreation Center located at 105 S Park Road, Tiffin, IA. The original contract sum
is $12,435,142.00, with no approved change orders to date.
Pay Application Summary
• Application No.: 4
• Period Ending: August 31, 2025
• Total Completed & Stored to Date: $546,403.26
• Retainage (5%): $27,320.17
• Total Earned Less Retainage: $519,083.09
• Less Previous Payments: $497,237.13
• Current Payment Due: $21,845.96
Work Progress
This pay application reflects progress on several line items including:
• General Conditions and Requirements
• Construction Fee
• Preconstruction Services
• Railroad Insurance
• Earthwork and Site Utilities
• Testing & Inspections Allowance
No new change orders have been submitted or approved during this period.
Recommendation
Staff recommends approval of Pay Application #4 in the amount of $21,845.96 to Miron
Construction Co., Inc. for work completed through August 31, 2025, as certified by Atura
Architecture.
ATTACHMENTS: Pay Application #4
1
Sources
- revize: Attachment (puHyqU2VMW3heCeYZYM6Zz1aM35LRF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Pay App 4 - Miron - Tiffin Recreation Center .pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #4 – Miron Construction, Tiffin...
Data last updated October 14, 2026. Built from the archive's documents; see how the data is built.