Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 09/05/2025
Miron Construction Co., Inc. Data Date: 05-Sep-25
Page 3 of 6
250120-15PM 20250905
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2540 MIRON CONC 1350 2550, Form and Pour Footings - Sequence 2 (Teal) 4 4 29-Sep-25 02-Oct-25
2630
2570 MIRON CONC 1350 2620, Form and Pour Footings - Sequence 1A & 1B Elevator (Brown) 5 5 29-Sep-25 03-Oct-25
2610,
2610 MIRON CONC 2570 2600
2700 Form and Pour Footings - Sequence 1C (Orange) 2 2 01-Oct-25 02-Oct-25
2550 MIRON CONC 2540 2560, Form and Pour Footings - Sequence 3 (Light Orange) 4 4 03-Oct-25 08-Oct-25
2640
2600 MIRON CONC 2570 2690 Form and Pour Footings - Sequence 1D (Purple) 2 2 03-Oct-25 06-Oct-25
2700 MIRON CONC 2610 2740 Form/Pour/Strip Foundation Wal s - Sequence 2 (Interior 3 3 03-Oct-25 07-Oct-25
Orange)
2620 MIRON CONC 2570, 2730, Form/Pour/Strip Foundation Wal s - Sequence 1 Elevator 5 5 06-Oct-25 10-Oct-25
2360 2630 (Brown)
2690 MIRON CONC 2600 2740 Form/Pour/Strip Foundation Wal s - Sequence 3 (Purple) 4 4 07-Oct-25 10-Oct-25
2560 MIRON CONC 2550 2580, Form and Pour Footings - Sequence 4 (Teal) 4 4 09-Oct-25 14-Oct-25
2650
2630 MIRON CONC 2540, 2640, Form/Pour/Strip Foundation Wal s - Sequence 4 (Teal) 4 4 13-Oct-25 16-Oct-25
2620 2740
2580 MIRON CONC 2560 2590, Form and Pour Footings - Sequence 5 (Green) 4 4 15-Oct-25 20-Oct-25
2660
2640 MIRON CONC 2550, 2750, Form/Pour/Strip Foundation Wal s - Sequence 5 (Light Orange) 4 4 17-Oct-25 22-Oct-25
2630 2650
2730 CORRIDORCOAT 2620 2740 Elevator Shaft Waterproofing 1 1 20-Oct-25 20-Oct-25
2740 SCHRADER 2730, 2070, Backfil Foundation Sequence 1,2,3,4 2 2 21-Oct-25 22-Oct-25
2700, 1380
1380 AAAMECH 2630,
2740 2800 Plumbing Underground 10 10 23-Oct-25 05-Nov-25
2070 SEEHASE 2740 2100 Elevator Shaft 5 5 23-Oct-25 29-Oct-25
2650 MIRON CONC 2560, 2660, Form/Pour/Strip Foundation Wal s - Sequence 6 (Orange) 4 4 23-Oct-25 28-Oct-25
2640 2750
2660 MIRON CONC 2580, 2760, Form/Pour/Strip Foundation Wal s - Sequence 7 (Pink) 4 4 29-Oct-25 03-Nov-25
2650 2670
2750 SCHRADER 2640, 1370, Backfil Foundation Sequence 5 & 6 2 2 29-Oct-25 30-Oct-25
2650 2810,
2100 SEEHASE 2070 2710, First Course CMU Bearing Wal s 3 3 30-Oct-25 03-Nov-25
2810 SCHRADER 2750 2590 Excavate Foundations (Footings Sequence 6) 1 1 31-Oct-25 31-Oct-25
2590 MIRON CONC 2580, 2680, Form and Pour Footings - Sequence 6 (Yel ow) 3 3 03-Nov-25 05-Nov-25
2810 2710
2670 MIRON CONC 2660 2760 Form/Pour/Strip Foundation Wal s - Sequence 8 (Green) 4 4 04-Nov-25 07-Nov-25
2680 MIRON CONC 2590 2770 Form/Pour/Strip Foundation Wal s - Sequence 9 (Yel ow) 4 4 06-Nov-25 11-Nov-25
2710 MIRON CONC 2590, 2790, Form/Pour/Strip Foundation Wal s - Sequence 10 (East Stoop 3 3 06-Nov-25 10-Nov-25
2750 2720 and Mechancial Pad)
2800 SCHRADER 1380 2820 Rock Base Course - Locker Room 1 1 06-Nov-25 06-Nov-25
2820 MIRON CONC 2800 2000, Prep/Pour Locker Room 2 2 07-Nov-25 10-Nov-25
1470
2760 SCHRADER 2660, 1370 Backfil Foundation Sequence 7 & 8 2 2 10-Nov-25 11-Nov-25
2670
2720 MIRON CONC 2710, 2790 Form/Pour/Strip Foundation Wal s - Sequence 11 (South Stoop 5 5 11-Nov-25 17-Nov-25
2750 and Mechancial Pads)
1460 SCHRADER 2770 1370 Rock Base Course 5 5 12-Nov-25 18-Nov-25
2770 SCHRADER 2680 1460, Backfil Foundation Sequence 9 (Yel ow) 2 2 12-Nov-25 13-Nov-25
1370
2790 SCHRADER 2710, 1590 Backfil and Subgrade Sequence 10 & 11 3 3 18-Nov-25 20-Nov-25
2720
Actual Work Please review the activities for which you are responsible and the relationships to the activities of other
Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Critical Remaining Work we receive no comments from you by 5 workings days, we will assume a lack of response to be your
Milestone agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.