packet

Packet: Regular City Council Meeting (09/16/2025)

Open the PDF

Page 68 of 77

Text from the PDF text layer; check the PDF for anything that matters.
Contract Summary Contract Summary Contingency Summary Original Contract Amount: $12,435,142.00 Original Contract Amount: $567,585.00 Change Orders to Date: $0.00 Change Orders to Date: $2,699.80 Current Contract Value: $12,435,142.00 Current Contract Value: $570,284.80 Current Scope Revisions Date Allowance Contingency Estimated Description Number Submitted Status Item? Item? Cost Impact 100% IFC Set - Civil BP1 (Add Fire Protection Line) 001 6/16/2025 Approved Yes Yes $7,300.12 ASI-01 Civil Utility Information 002 7/3/2025 Approved $0.00 Bid Package #2 Bid Documents and Drawing Updates 003 9/8/2025 In Review $0.00 Finalize Contract Budgets from Bid Package #2 004 8/21/2025 Approved $0.00 BP #2 Contract Reconciliation 005 In Review -$1,042,000.00 ASI-02 Transformer Pad, Changes Related to PEMB, Changes Related to Elevator 006 Collecting Pricing Owner Progress Report | 250120 August 2025 Miron Construction Co., Inc. | 10

Sources

  • revize: Agenda packet (packet_2025-09-16_909a3a8c-223b-4913-90b6-b5e14c757333.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 17, 2026. Built from the archive's documents; see how the data is built.