Packet: Regular City Council Meeting (09/16/2025)
Dated September 16, 2025City Council — regular meeting, September 16, 2025 77 pages
Ord. 2006-277, Res. 2025-075
Page 64 of 77
Text from the PDF text layer; check the PDF for anything that matters.Design/Action Items
Accomplishments
• Bid package 2 was sent out
• Final coordination items between disciplines
• ASI-2 has been sent out. This updated bid package 1 submittals to reflect on contract drawings
Upcoming Submittals/Design Deliverables
• Preliminary pre-engineered building calculations
• Rebar and foundation shop drawings
• Aggregate pier shop drawing
• CMU rebar shop drawing
• Long lead MEP equipment submittals
Submittals
• Working together to determine importance of incoming submittals from above
Requests for Information
• 7 Total RFI’s
• 5 RFI’s this month
• 2 Pending answers
‒ 0 over due
Areas of Concern / Focus
• Staying on top of submittals that are critical to upcoming work
• Finalizing color selections of flooring with the owner
Get involved, respond with
urgency, and work as a team
to get the job done. Leverage
the strengths of each
individual and overcome
obstacles as one.
Owner Progress Report | 250120 August 2025 Miron Construction Co., Inc.