Resolution 2025-075 – Resolution Setting as Public Hearing to Consider Adoption of an Updated Floodplain Management Ordinance for the City of Tiffin, Iowa.
Page 14 of 20
Text from the PDF text layer; check the PDF for anything that matters. optionally floodproofed to) a minimum of one (1) foot above the base flood
elevation.
(4) New and substantially improved structures shall be constructed with
plumbing, gas lines, water/gas meters and other similar service utilities either
elevated (or in the case of non-residential structures, optionally floodproofed to) a
minimum of one (1) foot above the base flood elevation or designed to be
watertight and withstand inundation to such a level.
E. Factory-Built Homes:
(1) All new and substantially improved factory-built homes, including those
placed in existing factory-built home parks or subdivisions, shall be elevated on a
permanent foundation such that the lowest floor of the structure is a minimum of
one foot above the base flood elevation.
(2) All new and substantially improved factory-built homes, including those
placed in existing factory-built home parks or subdivisions, shall be anchored to
resist flotation, collapse, or lateral movement. Anchorage systems may include,
but are not limited to, use of over-the-top or frame ties to ground anchors as
required by the State Building Code.
F. Utility and Sanitary Systems:
(1) On-site waste disposal and water supply systems shall be located or
designed to avoid impairment to the system or contamination from the system
during flooding.
(2) All new and replacement sanitary sewage systems shall be designed to
minimize or eliminate infiltration of flood waters into the system as well as the
discharge of effluent into flood waters. Wastewater treatment facilities (other than
on-site systems) shall be provided with a level of flood protection equal to or
greater than one foot above the base flood elevation.
(3) New or replacement water supply systems shall be designed to minimize
or eliminate infiltration of flood waters into the system. Water supply treatment
facilities (other than on-site systems) shall be provided with a level of protection
equal to or greater than one foot above the base flood elevation.
(4) Utilities such as gas or electrical systems shall be located and constructed
to minimize or eliminate flood damage to the system and the risk associated with
such flood damaged or impaired systems.
G. Storage of Equipment and Materials. Storage of equipment and materials that are
flammable, explosive, or injurious to human, animal, or plant life is prohibited unless
elevated a minimum of one foot above the base flood elevation. Other material and
equipment must either be similarly elevated or:
(1) Not subject to major flood damage and anchored to prevent movement due to flood
waters; or
(2) Readily removable from the area within the time available after flood warning.
H. Flood Control Structures. Flood control structural works such as levees, flood
walls, etc. shall provide, at a minimum, protection from the base flood with a minimum of
three feet of design freeboard and shall provide for adequate interior drainage. In addition,
the Department of Natural Resources shall approve structural flood control works.
cty_hr_d_160.doc - 11 - 4/15/2021
Sources
- revize: Attachment (r8tH6mfN5lJMEm4ci1rr8ZEYkapsgp.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (I-1 - Staff Report - Resolution 2025-075 - Setting PH - Floodplain Ordinance Amendment.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Resolution 2025-075 – Resolution Setting as Public Hearing to Consider Adoption of an...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.