Text read by OCR; check the PDF for anything that matters. CHANGE ORDER
DATE: 9/24/2025
Change Order No: _8 (EIGHT)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization — Phase 3 HFC #18218.131
OWNER: Tiffin, [A
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Reconstruction of sewer service to 230 W. 3rd Street and 230 College Street. See attached detailed
work description.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $ 2,134,856.90
CONTRACT with LAST CHANGE ORDER: _$ 2,295,348.91
THIS CHANGE ORDER AMOUNT: $17,199.61
NEW CONTRACT PRICE: $ 2,312,548.52
CONTRACT TIME CHANGES
CONTRACT TIME(increased) (decreased): 2 Days
NEW Completion Date: October 2, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See attached
ENGINEER: WIFE
Pe re
74
HFC #18218.131
CHANGE ORDER
Sources
- revize: Agenda packet (packet_2025-10-07_5ff2f89c-07cb-45dc-8618-9295e210d4d5.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.