contract agreement · K-4

Discussion and Consideration of Pay Application #7 – Boomerang Corporation, North Park Road Improvements Project – Motion to Approve

Open the PDF

Page 5 of 19

Text from the PDF text layer; check the PDF for anything that matters.
Total Current Previous Total Current Total Line Authorized Quantity Item ID Unit Unit Price Paid Paid Quantity Payment Amount Number Quantity Placed To Quantity Quantity Paid To Date Amount Paid To Date Date 0220 2402-2720100 CY $4.000 610.000 0.000 0.000 0.000 0.000 $0.00 $0.00 EXCAVATION, CLASS 20, FOR ROADWAY PIPE CULVERT 0230 2403-0100020 CY $840.000 149.400 0.000 149.400 149.400 149.400 $0.00 $125,496.00 STRUCTURAL CONCRETE (RCB CULVERT) 0240 2403-7303000 SY $27.500 901.000 0.000 0.000 0.000 0.000 $0.00 $0.00 STRUCTURAL CONCRETE COATING 0250 2404-7775000 LB $2.300 21,166.000 0.000 21,166.000 21,166.000 21,166.000 $0.00 $48,681.80 REINFORCING STEEL 0260 2414-6444100 LF $200.000 168.000 0.000 0.000 0.000 0.000 $0.00 $0.00 STEEL PIPE PEDESTRIAN HAND RAILING 0270 2415-2151212 LF $2,000.000 224.000 0.000 224.000 224.000 224.000 $0.00 $448,000.00 PRECAST REINFORCED CONCRETE PEDESTRIAN TUNNEL, 12 FT. X 12 FT. 0280 2416-0100030 EACH $3,800.000 1.000 0.000 1.000 1.000 1.000 $0.00 $3,800.00 APRONS, CONCRETE, 30 IN. DIA. 0290 2416-0100042 EACH $4,400.000 1.000 0.000 0.000 0.000 0.000 $0.00 $0.00 APRONS, CONCRETE, 42 IN. DIA. 0300 2416-0100072 EACH $7,200.000 1.000 0.000 0.000 0.000 0.000 $0.00 $0.00 APRONS, CONCRETE, 72 IN. DIA. 0310 2416-1180072 LF $400.000 339.000 0.000 0.000 0.000 0.000 $0.00 $0.00 CULVERT, CONCRETE ROADWAY PIPE, 72 IN. DIA. Detailed Payment: 10/01/2025 52-7662-615 Page 4 of 17

Sources

  • revize: Attachment (e3khg68cpi1xG9GoBFWUYqGIYXVXcS.pdf) — where it was found ↗ first seen Oct 12, 2026
  • sharepoint (K-4 - Staff Report - Pay App #7 - Boomerange Corp - Nort Park Road Construction.pdf) — where it was found ↗ first seen Oct 12, 2026

Attached to agenda item: Discussion and Consideration of Pay Application #7 – Boomerang Corporation, North Park...

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.