contract agreement · K-4
Discussion and Consideration of Pay Application #7 – Boomerang Corporation, North Park Road Improvements Project – Motion to Approve
Page 16 of 19
Text from the PDF text layer; check the PDF for anything that matters. Total
Current Previous Total Current Total
Line Authorized Quantity
Item ID Unit Unit Price Paid Paid Quantity Payment Amount
Number Quantity Placed To
Quantity Quantity Paid To Date Amount Paid To Date
Date
8080 2599-9999010 LS $116,000.000 1.000 0.569 0.431 1.000 1.000 $66,000.00 $116,000.00
('LUMP SUM' ITEM): ROUNDABOUT LIGHTING SYSTEM
8090 2602-0000530 EACH $192.500 5.000 5.000 0.000 5.000 5.000 $962.50 $962.50
GRATE INTAKE SEDIMENT FILTER BAG, EC-604
8100 2602-0000540 EACH $5.500 5.000 0.000 0.000 0.000 0.000 $0.00 $0.00
MAINTENANCE OF GRATE INTAKE SEDIMENT FILTER BAG
8110 2602-0000550 EACH $5.500 5.000 0.000 0.000 0.000 0.000 $0.00 $0.00
REMOVAL OF GRATE INTAKE SEDIMENT FILTER BAG
8120 2528-8400048 LF $99.000 50.000 0.000 0.000 0.000 0.000 $0.00 $0.00
TEMPORARY BARRIER RAIL, CONCRETE
Section Totals: $171,277.61 $2,961,703.09
Total Payments: $171,277.61 $2,961,703.09
Time Charges
Charges Damages Days Days
Original Authorized Damages
Time Limit This This Completed Remaining
Deadline Deadline To Date
Period Period To Date To Date
Working Days, Late Start Date - 04/07/2025, Liquidated Damage Rate - 200.0
202.0 Days 11.0 Days $0.00 82.5 Days 119.5 Days $0.00
2,000 Days
Total Damages: $0.00
Detailed Payment: 10/01/2025
52-7662-615 Page 15 of 17
Sources
- revize: Attachment (e3khg68cpi1xG9GoBFWUYqGIYXVXcS.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Staff Report - Pay App #7 - Boomerange Corp - Nort Park Road Construction.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #7 – Boomerang Corporation, North Park...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.