Discussion and Consideration of Pay Application #2 – Tricon Construction Group, Water Treatment Plant Upgrades – Motion to Approve
Page 1 of 12
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-3
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 3, 2025
AGENDA ITEM: Discussion and Consideration of Pay Application #2 – Tricon Construction
Group – Water Treatment Plant Upgrade
ACTION: Approval
Purpose
To request Council approval of Pay Application #2 from Tricon Construction Group for work
completed on the Water Treatment Plant Upgrades project.
Background
Tricon Construction Group is under contract with the City of Tiffin for the Water Treatment
Plant Upgrades project. The original contract amount is $12,182,553.00, with a net change order
of $12,420.34, bringing the current contract total to $12,194,973.34.
Pay Application #2 covers the period from August 1, 2025 to September 30, 2025, and includes:
• Total work completed and materials stored to date: $801,683.84
• Retainage (5%): $40,084.19
• Amount eligible to date (less retainage): $761,599.65
• Less previous payments: $458,122.32
• Amount due this application: $303,477.33
The application has been reviewed and recommended for approval by MSA Professional
Services, the City’s engineering consultant.
Recommendation
Staff recommends approval of Pay Application #2 in the amount of $303,477.33 to Tricon
Construction Group for work completed on the Water Treatment Plant Upgrades project.
ATTACHMENTS: Pay App
1
Sources
- revize: Attachment (sJkAosKmF3YbZCU8nafSLzkrjB6ds2.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-3 - Staff Report - Pay App #2 - Tricon Construction Group - Water Treatment Plant Upgrades.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #2 – Tricon Construction Group, Water...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.