PROJECT UPDATE
NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS
During the week of October 20th, Boomerang mobilized equipment to the site and informed MSA that
crews would be “moving some dirt around” on the west side of the road south of Mopar Drive. It was later
observed that previously installed erosion control measures had been removed, and grading had occurred
within the blue line stream area. This work proceeded without prior notification to MSA staff and without
the installation of erosion control measures required by Iowa DNR and Army Corps of Engineers permits.
As a result, a notice of noncompliance was issued.
MSA made further efforts to contact Boomerang project managers to better understand the intent of the
work. However, no explanation was received, and work continued without the necessary erosion control
measures, leading to a second noncompliance notice and an associated fine.
On the morning of October 27th, a meeting was held with Boomerang project managers to clarify erosion
control requirements for the site. Rock check dams were agreed upon as the appropriate measure to
prevent sediment pollution of the stream. As of October 30th, the rock check dams have been installed.
MSA staff will continue to monitor the site and conduct weekly erosion and traffic control inspections
throughout the winter. Boomerang will be notified if any corrective actions are needed to maintain
compliance with permit requirements and traffic safety. Recent work and future work in the month of
November is not expected to affect traffic on North Park Road.
Payment Applications will be submitted each month throughout the winter when work has been done. If
no work is done, the City will be informed that no Payment Application is required.
VILLAGE DRIVE & ROBERTS FERRY ROAD SIGNAL DESIGN – CHAD WAGNER
MSA has completed the preliminary operations analysis, which is currently under internal review. The initial
study findings will be shared with the City within the next two weeks. A meeting with the City will be
scheduled for early November. Preliminary signal pole locations and signal head placements are being
discussed based on the study’s initial findings.
PROJECT UPDATE
Page 2 of 4
Sources
- revize: Attachment (aikHl0ppKIEfzgXckn6yTCzmUqaSxS.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-1 - Engineer's Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.