Text from the PDF text layer; check the PDF for anything that matters. 3. Economic Development Grant Disbursement Request and Public
Infrastructure Costs Documentation. The Developer agrees to submit a grant
disbursement request (the “Grant Disbursement Request”) in the form attached hereto as Exhibit
B. The Grant Disbursement Request shall be accompanied by documentation (the “Costs
Documentation”) detailing the costs (the “Public Infrastructure Costs”) incurred in the
completion of the Public Infrastructure Project, including invoices and such other documentation
as is reasonably requested by the City, confirming that such Public Infrastructure Costs detailed
in such Costs Documentation were in fact incurred in the construction of the Public
Infrastructure Project and that such Public Infrastructure Costs are of an amount reasonably to
have been expected with respect to such construction.
The Public Infrastructure Costs may include costs related to designing, constructing,
landscaping, and grading the Public Infrastructure Project, as well as other reasonably related
costs of carrying out the Public Infrastructure Project.
4. Property Taxes. The Developer agrees to make timely payment of all
property taxes as they come due with respect to the Property throughout the Term (as hereinafter
defined) of this Agreement and to submit a receipt or cancelled check in evidence of each such
payment.
5. Default Provisions.
A. Events of Default. The following shall be “Events of Default” under this
Agreement, and the term “Event of Default” shall mean, whenever it is used in this Agreement
(unless otherwise provided), any one or more of the following events:
(i) Failure by the Developer to dedicate the Public Infrastructure Project to
the City pursuant to the terms and conditions of this Agreement.
(ii) Failure by the Developer to fully and timely remit payment of property
taxes when due and owing as required by this Agreement.
(iii) Failure by the Developer to comply with Section A.3 of this Agreement.
(iv) Failure by the Developer to observe or perform any other material
covenant on its part, to be observed or performed hereunder.
B. Notice and Remedies. Whenever any Event of Default described in this
Agreement occurs, the City shall provide written notice to the Developer describing the cause of
the default and the steps that must be taken by the Developer in order to cure the default. The
Developer shall have thirty (30) days after receipt of the notice to cure the default or to provide
assurances satisfactory to the City that the default will be cured as soon as reasonably possible.
If the Developer fails to cure the default or provide assurances, the City shall then have the right
to:
(i) Pursue any action available to it, at law or in equity, in order to enforce the
terms of this Agreement.
(ii) Withhold the Grant provided for under Section B.2 below.
(iii) Terminate this Agreement.
-2-
Sources
- revize: Attachment (GCiQK7Zp16sXGTrGWzUcDkofPXY6ZA.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (I-4 - Resolution 2025-085 – Economic Development Grant Agreemtn - Honey Lane.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Resolution 2025-085 – A Resolution Authorizing Economic Development Grant Agreement...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.