Discussion and Consideration of Change Order #9 – Rathje Construction, Original Town Urbanization Project Phase 3 – Motion to Approve
Page 2 of 3
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 11/12/2025
Change Order No: 9 (NINE)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131
OWNER: Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Add contract item for Full Depth PCC Pavement Patching, 9-Inch. Most of the additional cost is offset by deductions for work quantities not installed. See attached detailed work description.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $2,134,856.90
CONTRACT with LAST CHANGE ORDER: $2,312,548.52
THIS CHANGE ORDER AMOUNT: $18,836.61
NEW CONTRACT PRICE: $2,331,385.13
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 2 Days
NEW Completion Date: October 4, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See attached
ENGINEER: ________________________________
Sources
- revize: Attachment (NJBqp25xVjOvYFwkulARSqzAYFHi4z.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-2 - Change Order #9 - Rathje.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #9 – Rathje Construction, Original Town...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.