CITY OF TIFFIN CITY ADMINISTRATOR REPORT TO THE CITY COUNCIL November 26, 2025 • L.L. Pelling has finished the second asphalt lift on Main Street, Grant Street and West Third Street. The concrete work at the remaining intersections has also been completed as well as the concrete patch replacement on West Third Street. General clean-up for the winter is now taking place which leaves final grading and seeding as the majority of the work left to be completed in the spring. • Work continues to progress nicely for the recreation center. The building has started to go vertical with more steel beams being erected every day. This process should be completed in about a month. The next major project task will be the roof and the interior walls. • Last week was the 90% plans review meeting for the roundabout project at Forevergreen Road and Jasper Avenue. The project continues to be on schedule with a letting date of January 15, 2026. Work will begin right away in the spring. • The Special Census has resumed. The self-response period has closed with the City reaching 43%. This may not seem like a very high number but the original goal established by the census bureau was 44.1%. Even with the week that was lost due to the government shutdown, residents responded very well. Census field representatives should be in town the middle of December.

Sources

Attached to agenda item: M Reports from City Personnel

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.