Text from the PDF text layer; check the PDF for anything that matters. CITY OF TIFFIN
CITY ADMINISTRATOR
REPORT TO THE CITY COUNCIL
November 26, 2025
• L.L. Pelling has finished the second asphalt lift on Main Street, Grant Street and West
Third Street. The concrete work at the remaining intersections has also been completed
as well as the concrete patch replacement on West Third Street. General clean-up for the
winter is now taking place which leaves final grading and seeding as the majority of the
work left to be completed in the spring.
• Work continues to progress nicely for the recreation center. The building has started to
go vertical with more steel beams being erected every day. This process should be
completed in about a month. The next major project task will be the roof and the interior
walls.
• Last week was the 90% plans review meeting for the roundabout project at Forevergreen
Road and Jasper Avenue. The project continues to be on schedule with a letting date of
January 15, 2026. Work will begin right away in the spring.
• The Special Census has resumed. The self-response period has closed with the City
reaching 43%. This may not seem like a very high number but the original goal
established by the census bureau was 44.1%. Even with the week that was lost due to
the government shutdown, residents responded very well. Census field representatives
should be in town the middle of December.
Sources
- revize: Attachment (dAuM1FY8aYSTzgPew6np46TBigiyRj.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (M-10 - CMReport - 11-26-25.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: M Reports from City Personnel
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.