Discussion and Consideration of Pay Application #4 – Tricon Construction Group, Water Treatment Plant Upgrades Project – Motion to Approve
Page 9 of 12
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>Application No.: 4R</th>
<th>Application Period:</th>
<th>From</th>
<th>10/24/25</th>
<th>To</th>
<th>11/30/25</th>
<th>Application Date:</th>
<th>11/21/25</th>
</tr>
<tr>
<td>180</td>
<td>Bldg 10 - Foundations (Exc&BF)</td>
<td>$25,630.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>25,630.00</td>
</tr>
<tr>
<td>181</td>
<td>Bldg 20 - RO Fundations (Exc&BF)</td>
<td>$45,250.00</td>
<td>30,616.00</td>
<td></td>
<td></td>
<td></td>
<td>14,634.00</td>
</tr>
<tr>
<td>182</td>
<td>Bldg 20 - Aeration Tank Found (Ex&BF)</td>
<td>$15,640.00</td>
<td>9,384.00</td>
<td></td>
<td></td>
<td></td>
<td>6,256.00</td>
</tr>
<tr>
<td>183</td>
<td>Bldg 30 - Foundations (Exc&BF)</td>
<td>$37,850.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>37,850.00</td>
</tr>
<tr>
<td>184</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>185</td>
<td><b>Exterior Improvements</b></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>186</td>
<td>Asphalt Paving (Trail)</td>
<td>$22,130.00</td>
<td>22,130.00</td>
<td></td>
<td></td>
<td></td>
<td>22,130.00</td>
</tr>
<tr>
<td>187</td>
<td>Concrete Paving (Site)</td>
<td>$130,288.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>130,288.00</td>
</tr>
<tr>
<td>188</td>
<td>Chain Link Fencing</td>
<td>$32,250.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>32,250.00</td>
</tr>
<tr>
<td>189</td>
<td>Seeding</td>
<td>$6,914.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>6,914.00</td>
</tr>
<tr>
<td>190</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>191</td>
<td><b>Utilities</b></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>192</td>
<td>A - 12" W to Clearwell</td>
<td>$32,544.00</td>
<td>29,289.60</td>
<td></td>
<td></td>
<td></td>
<td>3,254.40</td>
</tr>
<tr>
<td>193</td>
<td>B - 8" W to Clearwell</td>
<td>$25,663.00</td>
<td>20,530.40</td>
<td></td>
<td></td>
<td></td>
<td>5,132.60</td>
</tr>
<tr>
<td>194</td>
<td>C - UG Storm Sewer North</td>
<td>$48,686.00</td>
<td>14,605.80</td>
<td>24,343.00</td>
<td></td>
<td></td>
<td>9,737.20</td>
</tr>
<tr>
<td>195</td>
<td>D - 12" W Aerator to Clearwell</td>
<td>$18,549.00</td>
<td>12,984.30</td>
<td>3,709.80</td>
<td></td>
<td></td>
<td>1,854.90</td>
</tr>
<tr>
<td>196</td>
<td>E - 12" W Bldg 10 to Bldg 20</td>
<td>$8,554.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>8,554.00</td>
</tr>
<tr>
<td>197</td>
<td>G - UG Storm Sewer East</td>
<td>$67,822.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>67,822.00</td>
</tr>
<tr>
<td>198</td>
<td>H & J - UG Storm Sewer West/South</td>
<td>$87,552.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>87,552.00</td>
</tr>
<tr>
<td>199</td>
<td>K - UG Storm Sewer Clearwell West</td>
<td>$42,500.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>42,500.00</td>
</tr>
<tr>
<td>200</td>
<td>F - UG Sanitary Manholes & Piping</td>
<td>$165,835.00</td>
<td>124,376.25</td>
<td>24,875.25</td>
<td></td>
<td></td>
<td>149,251.50</td>
</tr>
<tr>
<td>201</td>
<td>Roof Drains</td>
<td>$2,500.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>2,500.00</td>
</tr>
<tr>
<td>202</td>
<td>Bldg 20 - Process Drain Manhole</td>
<td>$8,500.00</td>
<td>6,375.00</td>
<td>2,125.00</td>
<td></td>
<td></td>
<td>8,500.00</td>
</tr>
<tr>
<td>203</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>204</td>
<td><b>Process Integration (Piping)</b></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>205</td>
<td>Structure 10 - Existing Bldg</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>206</td>
<td>Process Piping Materials</td>
<td>$55,103.74</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>55,103.74</td>
</tr>
<tr>
<td>207</td>
<td>Process Piping Labor</td>
<td>$37,550.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>37,550.00</td>
</tr>
<tr>
<td>208</td>
<td>Valves Materials</td>
<td>$9,500.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>9,500.00</td>
</tr>
<tr>
<td>209</td>
<td>Valves Labor</td>
<td>$8,250.28</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>8,250.28</td>
</tr>
<tr>
<td>210</td>
<td>Structure 20 - RO Building</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
</table>
Sources
- revize: Attachment (tIZLo8Sfu2gZWw01ErFfL4J4Rm10MP.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-6 - Pay Application #4 - Tricon - Water Treatment Plant Project.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-6 Discussion and Consideration of Pay Application #4 – Tricon Construction Group, Water...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.