contract agreement · K-6

Discussion and Consideration of Pay Application #4 – Tricon Construction Group, Water Treatment Plant Upgrades Project – Motion to Approve

Open the PDF Searchable (OCR) PDF

Page 12 of 12

Text read by OCR; check the PDF for anything that matters.
Progress Estimate - Lump Sum Work Contractor's Application for Payment Owner: City of Tiffin Owner's Project No.: Engineer's Project No.: 13603016 Engineer: | MSA Professional Services Contractor: Tricon Construction Group Contractor's Project No.: Project: Water Treatment Plant Upgrades - City of Tiffin Contract: Application Period: From 10/24/25 to 11/30/25 Application Date: 11/21/25 Application No.: 4R Change Orders 2 - Change Order #1 $12,420.34 - 12,420.34 Electrical Controls Changes Change Order Totals| $ 12,420.34 | $ - S$ - $ - $ - 0%| $ 12,420.34 Original Contract and Change Orders Project Totals| § _ 12,194,973.34 | $ 1,230,320.50 | $ 507,844.22 | $ 21,050.00 |$ — 1,759,214.72 14%| $ 10,435,758.62 00 62 76 - 10 of 10 \FILESERVER(Shares\Projects\Active\Tiffin WTP (25-012-1A)3-Tricon\Pay jons\Pay Application National Saclety of Profescional Engineer for ENCDCE Al ights reserved EJCDC* C-620 Contractor's Application for Payment

Sources

  • revize: Attachment (tIZLo8Sfu2gZWw01ErFfL4J4Rm10MP.pdf) — where it was found ↗ first seen Oct 12, 2026
  • sharepoint (K-6 - Pay Application #4 - Tricon - Water Treatment Plant Project.pdf) — where it was found ↗ first seen Oct 12, 2026

Attached to agenda item: K-6 Discussion and Consideration of Pay Application #4 – Tricon Construction Group, Water...

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.