contract agreement · K-3
Discussion and Consideration of Pay Application #7 – Miron Construction, Recreation Center – Motion to Approve
Page 1 of 4
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-3
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: November 26, 2025
AGENDA ITEM: Discussion and Consideration of Pay Application #7 Miron Construction –
Recreation Center Project
ACTION: Approval
Background
The City of Tiffin entered into a contract with Miron Construction Co., Inc. on November 19,
2024 for the construction of the Community Recreation Center located at 105 S Park Road,
Tiffin, IA. Atura Architecture serves as the project architect. The architect has certified that the
work completed is in accordance with contract documents and recommends payment.
Recommendation
Staff recommends approval of Pay Application #7 to Miron Construction Co., Inc. in the
amount of $631,874.08 for work completed on the Community Recreation Center project.
ATTACHMENTS: Pay Application
1
Sources
- revize: Attachment (OaMu0SW0AQA2bZmZnontJvnouEM0vn.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-3 - Pay Application #7 - Miron Construction - Recreation Center.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-3 Discussion and Consideration of Pay Application #7 – Miron Construction, Recreation...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.