Discussion and Consideration of Pay Application #9 – Boomerang Corporation, North Park Road Improvements Project – Motion to Approve
Page 19 of 20
Text from the PDF text layer; check the PDF for anything that matters.Summary
Current Approved Work: $176,759.15 Approved Work To Date: $3,205,977.04
Current Stockpile Advancement: $63,471.30 Stockpile Advancement To Date: $250,103.74
Current Stockpile Recovery: $0.00 Stockpile Recovery To Date: $86,063.90
Current Retainage: $0.00 Retainage To Date: $30,000.00
Current Retainage Released: $0.00 Retainage Released To Date: $0.00
Current Liquidated Damages: $0.00 Liquidated Damages To Date: $0.00
Current Adjustment: $0.00 Adjustments To Date: $0.00
Current Payment: $240,230.45 Payments To Date: $3,340,016.88
Previous Payment: $67,514.80 Previous Payments To Date: $3,099,786.43
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS: $176,759.15 52-7662-615-CAT-1 ROADWAY ITEMS To Date: $2,961,604.54
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2: $0.00 52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 To Date: $244,372.50
52-7662-615-CAT-3 NON-PARTICIPATING: $0.00 52-7662-615-CAT-3 NON-PARTICIPATING To Date: $0.00
Current Payment: $176,759.15 Payments To Date: $3,205,977.04
Detailed Payment: 11/20/2025
52-7662-615 Page 18 of 18
Sources
- revize: Attachment (dCzUNcZCZsE5fUqPMzwJ5cR6WYrZ84.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-2 - Pay Application #9 - Boomerang Corporation - North Park Road.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #9 – Boomerang Corporation, North Park...