Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-6
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 15, 2026
AGENDA ITEM: Approval of Pay Application #5 – Cornerstone Excavating, Inc – Earth
Stockpile Spread Project
ACTION: Motion
Background
The City has received Pay Application No. 5 from Cornerstone Excavating, Inc., for the Earth
Stockpile Spread project in Tiffin, Iowa. The application is dated September 24, 2026, and
reflects the completed contract work and approved change orders.
The original scope of work included Class 10 excavation, fertilizing and mulching, silt fence
installation, project management, and mobilization. Approved change-order items include junk
ditch cleanout and excess Class 10 excavation, additional silt fencing and silt fence removal,
hydraulic seeding and mulching, stormwater pollution prevention plan (SWPPP) management
and inspections, site regrading, and related credits for items not completed.
The payment application identifies the following amounts:
• Original Contract Sum: $138,050.00
• Net Change by Change Orders: $32,401.50
• Revised Contract Sum: $170,451.50
• Total Completed and Stored to Date: $170,451.50
• Retainage: $0.00
• Total Earned Less Retainage: $170,451.50
• Less Previous Certificates for Payment: $165,337.96
• Current Payment Due: $5,113.55
• Balance to Finish, Including Retainage: $0.00
The application indicates that the full revised contract amount has been completed and that no
remaining contract balance is outstanding following this payment.
Recommendation
Staff recommends approval of Pay Application No. 5 from Cornerstone Excavating, Inc., in the
amount of $5,113.55 for the Earth Stockpile Spread project.
ATTACHMENTS: Pay Application
1
Sources
- revize: E-6 (zBJlppjBoSzPKqrVOjsKMJlpSKa4OL.pdf) — where it was found ↗ first seen Oct 16, 2026
Attached to agenda item: E-6 Approval of Pay Application #5 – Cornerstone Excavating – Earth Stockpile Spread Project
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.