TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 15, 2026
AGENDA ITEM: Approval of Pay Application #17 – Miron Construction – Tiffin Recreation
Center Project
ACTION: Motion
Background
The City has received Pay Application No. 17 from Miron Construction Co., Inc., for
construction work completed on the Tiffin Community Recreation Center project.
The application reflects work completed during the current billing period, including progress on
general conditions, construction management, steel fabrication and erection, general trades,
athletic flooring, plumbing, HVAC, electrical, concrete site work, athletic turf surfacing, site
utilities, and landscaping.
The submitted application identifies the following project financials:
• Original Contract Sum: $12,435,142.00
• Net Change by Change Orders: ($1,042,001.88)
• Revised Contract Sum: $11,393,140.12
• Total Completed and Stored to Date: $10,040,922.57
• Retainage: $502,046.14
• Total Earned Less Retainage: $9,538,876.43
• Less Previous Certificates for Payment: $8,954,710.11
• Current Payment Due: $584,166.32
• Balance to Finish, Including Retainage: $1,854,263.69
Recommendation
Staff recommends approval of Pay Application No. 17 from Miron Construction Co., Inc., in the
amount of $584,166.32 for construction work completed on the Tiffin Community Recreation
Center project, subject to confirmation of the required payment certification and supporting
documentation.
ATTACHMENTS: Pay Application
1
Sources
- revize: E-5 (U0zMPy4geFLLCSsSxWym4Blbh9mNyd.pdf) — where it was found ↗ first seen Oct 16, 2026
Attached to agenda item: E-5 Approval of Pay Application #17 – Miron Construction – Tiffin Recreation Center Project
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.