Text from the PDF text layer; check the PDF for anything that matters. CHAPTER 96
BUILDING SEWERS AND CONNECTIONS
96.01 Permit 96.05 Excavations
96.02 Plumber Required 96.06 Inspection Required
96.03 Connection Requirements 96.07 Property Owner’s Responsibility
96.04 Sewer Tap 96.08 Abatement of Violations
96.01 PERMIT. No unauthorized person shall uncover, make any connection with or opening into, use,
alter, or disturb any public sewer or appurtenance thereof without first obtaining a written permit from the
City. The application for the permit shall set forth the location and description of the property to be
connected with the sewer system and the purpose for which the sewer is to be used, and shall be
supplemented by any plans, specifications, or other information considered pertinent. The permit shall
require the owner to complete construction and connection of the building sewer to the public sewer
within sixty (60) days after the issuance of the permit, except that when a property owner makes sufficient
showing that due to conditions beyond the owner’s control or peculiar hardship, such time period is
inequitable or unfair, an extension of time within which to comply with the provisions herein may be
granted. Any sewer connection permit may be revoked at any time for a violation of these chapters.
96.02 PLUMBER REQUIRED. The person who makes the application shall pay a fee in the amount
of $200.00 to the Clerk.
96.03 CONNECTION REQUIREMENTS. The installation of the building sewer and its connection
to the public sewer shall conform to the requirements of the International Plumbing Code, the laws of the
State and other applicable rules and regulations of the City, including the City Design Standards.
96.04 SEWER TAP. Connection of the building sewer into the public sewer shall be made at the “Y”
branch, if such branch is available at a suitable location. If no properly located “Y” branch is available, a
saddle “Y” shall be installed at the location specified by the Superintendent. The public sewer shall be
tapped with a tapping machine and a saddle appropriate to the type of public sewer shall be glued or
attached with a gasket and stainless steel clamps to the sewer. At no time shall a building sewer be
constructed so as to enter a manhole unless special written permission is received from the Superintendent
and in accordance with the Superintendent’s direction if such connection is approved.
96.05 EXCAVATIONS. All trench work, excavation, and backfilling required in making a connection
shall be performed in accordance with the provisions of the International Plumbing Code and the
provisions of Chapter 135 of this Code of Ordinances.
96.06 INSPECTION REQUIRED. No building sewer shall be covered, concealed, or put into use
until it has been tested, inspected and accepted as prescribed in the International Plumbing Code.
96.07 PROPERTY OWNER’S RESPONSIBILITY. All costs and expenses incident to the
installation, connection, and maintenance of the building sewer shall be borne by the owner. The owner
shall indemnify the City from any loss or damage that may directly or indirectly be occasioned by the
installation of the building sewer.
96.08 ABATEMENT OF VIOLATIONS. Building sewers, whether located upon the private property
of any owner or in the public right-of-way, which are constructed or maintained in violation of any of the
requirements of this chapter shall be deemed a nuisance and the same shall be abated by the City in the
manner provided for the abatement of nuisances.
(Code of Iowa, Sec. 364.12[3])