Text from the PDF text layer; check the PDF for anything that matters. RESOLUTION NO. 2025-
012
A RESOLUTION APPROVING THE SUBSTANTIAL COMPLETION FOR THE WELL
5 PUMP, CONTROLS AND WATERMAIN PROJECT
Whereas, the walk-
through and the creation of a punchlist has resulted in the
substantial completion of the Well 5 pump, controls and watermain project, and;
Whereas, Veenstra & Kimm made an on - site review of the completed construction of
Well 5 performed by Boomerang Corp. of Anamosa, Iowa and certified complete on
January 8, 2025;
Now, therefore be it resolved by the City Council of the City of Tiffin, Iowa to approve
the substantial completion for the Well 5 Pump, Controls and Watermain Project.
On the 21st day of January, 2025, at a regular meeting of the Tiffin City Council, Tiffin,
Iowa, Councilperson Limkemann introduced RESOLUTION NO. 2025-
012,A
RESOLUTION APPROVING THE SUBSTANTIAL COMPLETION FOR THE WELL 5
PUMP, CONTROLS AND WATERMAIN PROJECT and made a motion for approval.
Motion seconded by Councilperson Orris.
Ayes: Orris, Olney, Schnedler, Limkemann, Havens.
Nays: None.
Absent: None.
Whereupon five Council members were present and voted approval and Mayor
Kasparek declared that the RESOLUTION NO. 012,
2025- A RESOLUTION
APPROVING THE SUBSTANTIAL COMPLETION FOR THE WELL 5 PUMP,
CONTROLS AND WATERMAIN PROJECT to be adopted and signified his approval of
the same by affixing his signature thereto.
Passed by the City Council on the 21st day of January, 2025.
City a iffin
Tim Kasparek, May
ATTEST: . i
Abigail F ra, City Clerk
Sources
- laserfiche: Resolutions-2025-012 (Resolutions-2025-012.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.