City Engineer's Report
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell: 515.802.0906
[email protected]
DATE:
January 29, 2026
ON-GOING PROJECTS
REVERSE OSMOSIS WATER TREATMENT PLANT DESIGN – CLINT WIENEN
With the colder temps, the contractor has primarily been working on painting within the existing treatment
plant. They are scheduled to replace the media in the existing pressure filters within the next month. They
will also be pouring the foundation walls for the RO Building when they receive the embeds from the precast
wall manufacturer.
SYSTEMWIDE SANITARY SEWER MODEL – ERIC THOMPSON
MSA has completed the dry and wet weather calibration and started preparing documentation for the City.
The MSA staff who are completing the modeling will be presented to the City Administrator, focused on the
big picture overview the model development, the calibration, and existing conditions evaluation. The focus
will be on portions of the sanitary system that have limited capacity and might need to be upsized to
accommodate future growth.
VILLAGE DRIVE & ROBERTS FERRY ROAD SIGNAL DESIGN – CHAD WAGNER
Iowa DOT had no major comments or concerns regarding the design but want to verify that traffic control
details are shared with them for review prior to construction.
MSA is finalizing design and will submit to City Staff for review in early February and then move to bid the
project.
PROJECT UPDATE
Page 1 of 5
Sources
- revize: Attachment (B0hQQ858P8ZHFTlLTm1JT8gBIZrzyR.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 City Engineer's Report