Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades- City of Tiffin
Contract:
Application No.: 5 Application Period: From 12/01/25 to 01/23/26 Application Date: 01/23/26
ea L ee ChangeOrders :
Change Order #1 if a
Electrical Controls Changes $12,420.34 - 12,420.34
Change Order Totals| $ 12,420.34 | $ - $ - $ - 5 - 0%! $ 12,420.34
Original Contract and Change Orders
Project Totals| $ 12,194,973.34 | $ 1,738,164.72 | $ 160,160.06 | $ 21,050.00 |$ 1,919,374.78 16%| $ 10,275,598.56
EJCDC* C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved. 00 62 76-10 of 10 \\FILESERVER\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\Pay
ay
Sources
- revize: Attachment (GUawLCTfSkedSvwmNfkhpMbVvtw3E0.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-3 Consideration of Pay Application #5 – Tricon Construction Group – Water Treatment...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.