staff report memo · K-2
Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement Request #1 – Water Treatment Facility Upgrade Project – Motion to Approve
Page 5 of 66
Text from the PDF text layer; check the PDF for anything that matters. INVOICE
TO MAKE A PAYMENT BY CREDIT CARD, PLEASE
REQUEST A SECURE LINK VIA COLLECTIONS@MSA-
PS.COM. A 3% SERVICE FEE WILL BE ADDED TO
INVOICES PAID BY CREDIT CARD. PAST DUE BALANCES
ARE SUBJECT TO AN INTEREST RATE OF 1.5% PER
MONTH.
Invoice No: 025329
Invoice Date: 1/23/2026
City of Tiffin Invoice Terms: Due upon receipt
PO Box 259 Project No: R13603021.00
300 Railroad Street
Project Manager: Clint Wienen
Tiffin, IA 52340
Client Liaison: Andrew Inhelder
Customer Ref:
From 11/09/2025 To 01/03/2026
R13603021.00 Tiffin Water Treatment Facility Upgrade Bidding & CRS
Progress detail
Percent Previous Current Remaining
Phase Fee complete billing billing contract
Bidding 32,000.00 100.00% 32,000.00 0.00 0.00
Construction Administration 374,000.00 31.05% 104,256.66 11,862.34 257,881.00
Post Construction 44,000.00 0.00% 0.00 0.00 44,000.00
Subtotal 450,000.00 32.92% 136,256.66 11,862.34 301,881.00
R13603021.00.300 - RPR
Subtotal RPR 15,955.01
Total 27,817.35
Please include the MSA Invoice Number and Project Number with your payment.
ACH Payments: Check Payments:
[email protected] MSA
Account Number: 101065930 1230 South Boulevard
Baraboo, WI 53913
Routing Number: 075901590
Bank Information: ACH/Wire, Baraboo State Bank, 101 3rd Avenue
Baraboo, WI 53913
Sources
- revize: Attachment (26JocivB3GX4YblLGOV44P4O7G93q8.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.