Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 3 Application Period: From 10/01/25 to 10/23/25 Application Date: 10/23/25
:
Change Orders
Change Order #1 = E
Electrical Controls Changes $12,420.34 - 12,420.34
Change Order Totals} $ 12,420.34 | $ - $ - $ - $ - 0%| $ 12,420.34
Original Contract and Change Orders
Project Totals| $__12,194,973.34 | $ 801,683.84 | $ 395,804.97 | $ 32,831.69 |$ — 1,230,320.50 10%| $ 10,964,652.84
EJCDC* C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved. 00 62 76
- 10 of 10 \WFILESERVER\Shares\Projects\Active\Tiffin WTP (25-012-1A)\3-Tricon\PaymentApplications\Pay
Sources
- revize: Attachment (26JocivB3GX4YblLGOV44P4O7G93q8.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement...
Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.