Text read by the vision model; check the PDF for anything that matters.RESOLUTION NO. 2018-796
APPROVING AWARD OF CONTRACT FOR THE 2018 INTERSTATE WATERMAIN RELOCATION PROJECT FOR THE CITY OF TIFFIN, UPON REVIEW OF THE BIDS AND RECOMMENDATION BY THE PROJECT ENGINEER
WHEREAS, The City Council of the City of Tiffin has received bids for the 2018 Interstate Watermain Relocation Project; and
WHEREAS, the City of Tiffin has identified Dave Schmitt Construction of Cedar Rapids, Iowa as having the lowest, most responsible bid; and
WHEREAS, the City of Tiffin desires to expedite the contractual process; now
THEREFORE, BE IT RESOLVED by the City Council of the City of Tiffin to authorize the Mayor and City Clerk to sign all necessary notices, documents, and forms of contract, as required and necessary to execute a contract with Dave Schmitt Construction as identified and recommended by the Project Engineer.
PASSED AND APPROVED this 2nd Day of October, 2018.
AYE: Peggy Opton, Al Havens, Jim Bartels, Eric Schneidler
NAY: None
ABSENT: Mike Ryan
SIGNED: Steve Berner, Mayor
ATTEST: Doug Boldt, City Administrator