staff report memo · M-10
Reports from City Personnel — M.10
Page 1 of 3
Text from the PDF text layer; check the PDF for anything that matters. CITY OF TIFFIN
CITY ADMINISTRATOR
REPORT TO THE CITY COUNCIL
March 13, 2026
• We had the preconstruction meeting for the Forevergreen Road and Jasper Avenue
Improvements on Friday morning in North Liberty. The scheduled start date for the
project from the contractor is April 1st. The project’s substantial completion date is
November 15, 2026.
• Boomerang has started the next phase of the North Park Road Improvements project.
They have begun to remove the remaining pavement and will continue to work on the
area in and around the box culvert. Just as a reminder, a road closure map is included in
the packet which includes the detour route.
• On Wednesday, March 4th, Ashley and I both attended the Iowa League of Cities Local
Leaders Day at the capitol. It was a really good day in which we got updates on the
proposed bills that will directly affect cities and local government. And although brief,
we did get a chance to meet with State Senators Dawn Driscoll and Dan Dawson and
State Representative Amy Nielson.
• An item for a future work session that Brett would like to discuss is the potential of
preparing the second (pilot) water well that was identified when bringing on well #5.
Brett thinks once the new treatment plant project is completed, that might be the time to
look at the need and feasibility to bring that additional well online.
• Just a friendly reminder, Ashley will be at the Iowa Municipal Management Institute
Conference that is held in Iowa City from March 25th – 27th, and I will be in Arizona on
March 26th and 27th. Both of us will still be available by phone, text or email.
Sources
- revize: M.10 (8fbeeaQEsDYEriHwsyNLC2JVqUnxfr.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: M Reports from City Personnel
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.