contract agreement · K-2
Discussion and Consideration of Pay Application #10 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 19 of 20
Text from the PDF text layer; check the PDF for anything that matters.Summary
Current Approved Work: $33,600.00 Approved Work To Date: $3,239,577.04
Current Stockpile Advancement: -$937.66 Stockpile Advancement To Date: $249,166.08
Current Stockpile Recovery: $0.00 Stockpile Recovery To Date: $86,063.90
Current Retainage: $0.00 Retainage To Date: $30,000.00
Current Retainage Released: $0.00 Retainage Released To Date: $0.00
Current Liquidated Damages: $0.00 Liquidated Damages To Date: $0.00
Current Adjustment: $0.00 Adjustments To Date: $0.00
Current Payment: $32,662.34 Payments To Date: $3,372,679.22
Previous Payment: $240,230.45 Previous Payments To Date: $3,340,016.88
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS: $33,600.00 52-7662-615-CAT-1 ROADWAY ITEMS To Date: $2,995,204.54
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2: $0.00 52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 To Date: $244,372.50
52-7662-615-CAT-3 NON-PARTICIPATING: $0.00 52-7662-615-CAT-3 NON-PARTICIPATING To Date: $0.00
Current Payment: $33,600.00 Payments To Date: $3,239,577.04
Detailed Payment: 02/24/2026
52-7662-615 Page 18 of 18
Sources
- revize: K.2 (5sZSXYSRGbwadl4a9CbE2z8jZZ6NxI.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #10 – Boomerang Corporation – North...