Text from the PDF text layer; check the PDF for anything that matters. RESOLUTION NO. 2012 - 38
RESOLUTION ADOPTING PLANS, SPECIFICATIONS, AND FORM OF
CONTRACT FOR THE 2012 INDUSTRIAL PARK WATERMAIN
EXTENSION PROJECT FOR TIFFIN, IA.
WHEREAS, on this 8th day of August, 2012, Plans, Specifications and Form of Contract
were filed with the City of Tiffin for the construction of the 2012 Industrial Park Watermain
Extension Project within the City of Tiffin.
WHEREAS, a notice of hearing on these Plans, Specifications, and Form of Contract was
published as required by law, now,
THEREFORE, BE IT RESOLVED, BY The City of Tiffin that the said Plans, Specifications
and Form of Contract are hereby approved for said project.
PASSED AND APPROVED THIS
8TH DAY OF AUGUST, 2012
AYE: Ryan, Bartels, Weipert, Ball, Upton
NAY: none
ABSENT: none
SIGNED:
Steve Berner, Mayor
ATTEST:
son, City Administrator/ Clerk
HFC # 12218. 125
Sources
- laserfiche: Resolutions-2012-38 (Resolutions-2012-38.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.