staff report memo · K-6
Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement Request #3 – Water Treatment Facility Upgrade Project – Motion to Approve — K.6
Page 15 of 15
Text from the PDF text layer; check the PDF for anything that matters. INVOICE
TO MAKE A PAYMENT BY CREDIT CARD, PLEASE
REQUEST A SECURE LINK VIA COLLECTIONS@MSA-
PS.COM. A 3% SERVICE FEE WILL BE ADDED TO
INVOICES PAID BY CREDIT CARD. PAST DUE BALANCES
ARE SUBJECT TO AN INTEREST RATE OF 1.5% PER
MONTH.
Invoice No: 027238
Invoice Date: 3/23/2026
City of Tiffin Invoice Terms: Due upon receipt
PO Box 259 Project No: R13603021.00
300 Railroad Street
Project Manager: Clint Wienen
Tiffin, IA 52340
Client Liaison: Andrew Inhelder
Customer Ref:
From 02/08/2026 To 03/07/2026
R13603021.00 Tiffin Water Treatment Facility Upgrade Bidding & CRS
Progress detail
Percent Previous Current Remaining
Phase Fee complete billing billing contract
Bidding 32,000.00 100.00% 32,000.00 0.00 0.00
Construction Administration 374,000.00 39.30% 135,344.52 11,650.00 227,005.48
Post Construction 44,000.00 0.00% 0.00 0.00 44,000.00
Subtotal 450,000.00 39.78% 167,344.52 11,650.00 271,005.48
R13603021.00.300 - RPR
Subtotal RPR 9,996.08
Total 21,646.08
Please include the MSA Invoice Number and Project Number with your payment.
ACH Payments: Check Payments:
[email protected] MSA
Account Number: 101065930 1230 South Boulevard
Baraboo, WI 53913
Routing Number: 075901590
Bank Information: ACH/Wire, Baraboo State Bank, 101 3rd Avenue
Baraboo, WI 53913
Sources
- revize: K.6 (9xvwpqTcLqtJYXREIb0a0RiyGeR5wC.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-6 Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.