staff report memo · K-6

Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement Request #3 – Water Treatment Facility Upgrade Project – Motion to Approve — K.6

Open the PDF Searchable (OCR) PDF

Page 13 of 15

Text read by the vision model; check the PDF for anything that matters.
Progress Estimate - Lump Sum Work Owner: City of Tiffin Engineer: MSA Professional Services Contractor: Tricon Construction Group Project: Water Treatment Plant Upgrades - City of Tiffin Contract: Owner's Project No.: Engineer's Project No.: 13603016 Contractor's Project No.: Application No.: 7 Application Period: From 02/21/26 to 03/20/26 Application Date: 03/27/26 <table> <tr> <th colspan="8">Change Orders</th> </tr> <tr> <th>Change Order #1</th> <th></th> <th></th> <th></th> <th></th> <th></th> <th></th> <th></th> </tr> <tr> <td>Electrical Controls Changes</td> <td>$12,420.34</td> <td></td> <td></td> <td></td> <td></td> <td></td> <td>12,420.34</td> </tr> <tr> <td colspan="7"></td> <td></td> </tr> <tr> <td colspan="7">Change Order Totals</td> <td>$12,420.34</td> </tr> </table> <table> <tr> <th colspan="8">Original Contract and Change Orders</th> </tr> <tr> <th>Project Totals</th> <th>$12,194,973.34</th> <th>$2,333,704.91</th> <th>$244,060.08</th> <th>$283,320.20</th> <th>$2,861,085.19</th> <th>23%</th> <th>$9,333,888.15</th> </tr> </table>

Sources

Attached to agenda item: K-6 Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement...

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.