staff report memo · K-6
Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement Request #3 – Water Treatment Facility Upgrade Project – Motion to Approve — K.6
Page 13 of 15
Text read by the vision model; check the PDF for anything that matters.Progress Estimate - Lump Sum Work
Owner: City of Tiffin
Engineer: MSA Professional Services
Contractor: Tricon Construction Group
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Owner's Project No.:
Engineer's Project No.: 13603016
Contractor's Project No.:
Application No.: 7 Application Period: From 02/21/26 to 03/20/26 Application Date: 03/27/26
<table>
<tr>
<th colspan="8">Change Orders</th>
</tr>
<tr>
<th>Change Order #1</th>
<th></th>
<th></th>
<th></th>
<th></th>
<th></th>
<th></th>
<th></th>
</tr>
<tr>
<td>Electrical Controls Changes</td>
<td>$12,420.34</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>12,420.34</td>
</tr>
<tr>
<td colspan="7"></td>
<td></td>
</tr>
<tr>
<td colspan="7">Change Order Totals</td>
<td>$12,420.34</td>
</tr>
</table>
<table>
<tr>
<th colspan="8">Original Contract and Change Orders</th>
</tr>
<tr>
<th>Project Totals</th>
<th>$12,194,973.34</th>
<th>$2,333,704.91</th>
<th>$244,060.08</th>
<th>$283,320.20</th>
<th>$2,861,085.19</th>
<th>23%</th>
<th>$9,333,888.15</th>
</tr>
</table>
Sources
- revize: K.6 (9xvwpqTcLqtJYXREIb0a0RiyGeR5wC.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-6 Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.