Resolution No. 2026-022 – A Resolution Approving the Partial Release of the Escrow for 80/380 Commerce Park First Addition — I.3
Page 1 of 7
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # I-3
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: April 3, 2026
AGENDA ITEM: Resolution No. 2026-022 – A Resolution Approving the Partial Release of
the Escrow for 80/380 Commerce Park First Addition
ACTION: Motion
Background
The City Council approved the Final Plat for 80/380 Commerce Park First Addition on April 15,
2025. As a condition of that approval, the developer, 80/380 Commerce Park, LLC, entered into
an escrow agreement with the City in the amount of $419,890.86 to ensure completion of public
infrastructure improvements, including the Village Drive Extension.
A walkthrough of the Village Drive Extension was conducted, and follow-up inspections were
completed to evaluate construction status and remaining punch list items.
Staff is requesting City Council approval of Resolution No. 2026-022, approving a partial release
of escrow associated with the 80/380 Commerce Park First Addition. The escrow was
established at the time of final plat approval to guarantee completion of required on-site and
off-site public improvements. Based on inspections and recommendations from the City
Engineer, the majority of the improvements have been substantially completed, and a partial
release is appropriate at this time.
City staff and the City Engineer conducted site visits on February 6, 2026, with a subsequent
visit on April 2, 2026. As documented in the walkthrough and the Brain Engineering Status
Update dated April 2, 2026, the following summarizes the current project status:
• Major roadway, grading, stormwater, and utility infrastructure is substantially complete
• Testing has been completed and results submitted
• Construction debris removal, service stub verification, basin grading, outlet structure
installation, and apron trash guards have been completed
• Remaining items include:
o Monitoring of reseeded areas for stabilization
o Removal of erosion control after stabilization
o Installation of street signage, pavement markings, and street lighting
o Coordination on select tree removal and trimming
o Final confirmation that intake throat openings meet SUDAS standards
These remaining items are standard close-out activities and will remain secured by the remaining
escrow balance.
1
Sources
- revize: I.3 (uK0zcxsATwSGSVJpSd1nKr51gBfMDN.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: I-3 Resolution No. 2026-022 – A Resolution Approving the Partial Release of the Escrow for...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.