Discussion and Consideration of Pay Application #10 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.2
Page 10 of 17
Text read by OCR; check the PDF for anything that matters.CONTINUATION SHEET AIA DOCUMENT G703 (instructions on reverse side) PAGE OF PAGES
AIA Document G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing APPLICATION NUMBER: 2
Contractor's signed Certification is attatched. TIFFIN COMM. REC CENTER APPLICATION DATE: 2/19/2026
In tabulations below, amounts are stated to the nearest doliar. 25-508 PERIOD TO: 2/28/2026
Use Column | on Contracts where variable retainage for line items may apply. MIRON ARCHITECT'S PROJECT NO:
SCOTT
A B c 3] E F G H |
M DESCRIPTION OF WORK SCHEDULED WORK COMPLETED MATERIALS TOTAL % (GIC) BALANCE TO RETAINAGE
NO. VALUE FROM THIS PERIOD PRESENTLY |COMPLETED AND FINISH (C-G)
PREVIOUS STORED STORED TO
APPLICATION (NOT INDORE)}| DATE (D+E+F)
84113 ALUMINUM STOREFRONT & 084413 C.WALL
MATERIAL, $123,920.00 $91,000.00 $0.00 $0.00 $91,000.00} 73.4% $32,920.00 $4,550.00
LABOR $59,535.00 $0.00 $0.00 $0.00 0.0% $59,535.00 $0.00
087109 DOOR HARDWARE
MATERIAL $72,125.00 $0.00 $0.00 $72,125.00 $72,125.00] 100.0% $0.00 $3,606.25
LABOR $14,075.00 $0.00 $0.00 $0.00 0.0% $14,075.00 $0.00
088000 GLAZING
MATERIAL $64,555.00 $0.00 $0.00 $0.00 0.0% $64,555.00 $0.00
LABOR $26,450.00) $0.00 $0.00 $0.00 0.0% $26,450.00 $0.00
107316 CANOPIES
MATERIAL $19,690.00 $0.00 $0.00 $19,690.00 $19,690.00] 100.0% $0.00 $984.50
LABOR $8,950.00 $0.00 $0.00. $0.00 0.0% $8,950.00 $0.00
$389,300.00 $91,000.00 $0.00 $91,815.00 $182,815.00} 47.0% $206,485.00 $9,140.75
Sources
- revize: K.2 (8ML5xkHm6nq6U17AdBvw3UCIhe3sAu.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #10 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.